100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

C722 Project Management (highlighted study guide + JO's tips + practice test) Questions with Accurate Answers

Rating
-
Sold
-
Pages
51
Grade
A+
Uploaded on
02-07-2025
Written in
2024/2025

0-100 rule correct answer Assigns 0% to activities that have not been started and those that are in progress. Completed activities are assigned 100%. Every activity in the project is assigned a value of either 0% or 100%. 50/50 rule correct answer Assigns half completed as soon as an activity is started and fully completed when an activity is finished. 8/80 Rule correct answer A good rule of thumb - do not assign anything that takes less than 8 hours (to avoid micromanaging and ensure we give sufficient work out) and also do not assign anything that takes more than 80 hours to complete, or if you must, check in every 80 hours. A chain of grocery stores undertakes a project to replace card readers in their checkout lines with a new technology consistent with current banking regulations and encryption standards since the old technology is being phased out by their bank. What project selection model is being utilized in this situation? correct answer Operating necessity A large construction project to build apartments to house athletes for the upcoming Olympic games is underway. If anything starts getting off

Show more Read less
Institution
Project Managememt
Course
Project Managememt











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Project Managememt
Course
Project Managememt

Document information

Uploaded on
July 2, 2025
Number of pages
51
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

C722 Project Management (highlighted
study guide + JO's tips + practice test)
Questions with Accurate Answers

0-100 rule correct answer Assigns 0% to activities that have not been
started and those that are in progress. Completed activities are
assigned 100%. Every activity in the project is assigned a value of either
0% or 100%.


50/50 rule correct answer Assigns half completed as soon as an activity
is started and fully completed when an activity is finished.


8/80 Rule correct answer A good rule of thumb - do not assign anything
that takes less than 8 hours (to avoid micromanaging and ensure we
give sufficient work out) and also do not assign anything that takes
more than 80 hours to complete, or if you must, check in every 80
hours.


A chain of grocery stores undertakes a project to replace card readers
in their checkout lines with a new technology consistent with current
banking regulations and encryption standards since the old technology
is being phased out by their bank. What project selection model is
being utilized in this situation? correct answer Operating necessity


A large construction project to build apartments to house athletes for
the upcoming Olympic games is underway. If anything starts getting off

,track, which triple constraint would not be appropriate to adjust?
correct answer Time


A manufacturing company is reviewing potential projects for the
coming year based on the CEO's request to reduce overhead
costs.Which of the following projects would best align with the
company's desired business strategy? correct answer Replacing
warehouse lighting with higher efficiency bulbs and motion sensors


A new project manager is taking over for the previous PM who is no
longer with the company. As she starts getting to know the project
team, which of the following tools would give the new PM the best
snapshot of who all the project team members are and their individual
roles on the project? correct answer Resource responsibility matrix


A new project team is made up of people from several different
departments. Due to the way workspaces are designed and the number
of project team members, there is no space large enough for all team
members to meet together in their weekly meetings. What type of risk
is this? correct answer Organizational


A newly established PMO asks management, employees, and project
management staff to submit questions to be used as criteria for
prioritizing projects. They plan to use all submitted questions and
weight them based on how many people submit the same question.
What is the benefit of using this approach? correct answer Project
impact to all departments will be considered

,A newly established PMO asks management, employees, and project
management staff to submit questions to be used as criteria for
prioritizing projects. They plan to use all submitted questions and
weight them based on how many people submit the same question.
What type of project selection model is being used? correct answer
Checklist


A project is being proposed to restructure a manufacturing company's
assembly line to streamline processes per the request of the quality
staff. The following high-level WBS was created by the project manager
as part of the project charter to help management see the project
timeline before the detailed WBS is developed. Which network diagram
matches the table? correct answer A


A project manager and her team do a make/buy analysis and determine
that even though they have the expertise in-house to build a new
security system for the company's warehouse, they will outsource the
project to a vendor. The vendor has an existing product with full
technical support provided in the contract. What type of risk response
is this? correct answer Transfer


A project manager receives three estimates from the project team for
the amount of time it will take to replace the flooring in a renovation
project, depending on how much damage they find while doing their
demolition work. The pessimistic estimate is 18 days. The optimistic
estimate is 8 days. The most likely estimate is 10 days. What is the beta
distribution estimate for this task? correct answer 11 days

, A project manager receives three estimates from the project team for
the amount of time it will take to replace the flooring in a renovation
project, depending on how much damage they find while doing their
demolition work. The pessimistic estimate is 18 days. The optimistic
estimate is 8 days. The most likely estimate is 10 days. What is the
triangular distribution estimate for this task? correct answer 12 days


A project to open a new restaurant before the next holiday has a
penalty clause of $1000 per day if the contractor completes their work
late in order to account for lost sales. Which of the triple constraints
would be contractually adjusted if the launch date is missed? correct
answer Cost


A project to translate existing training materials for an international
subsidiary has been planned, and the following network diagram has
been submitted. How long will the project take based on the critical
path? correct answer 88 days


A project to translate existing training materials for an international
subsidiary has been planned, and the following network diagram has
been submitted. Which task has the largest amount of slack? correct
answer Train personnel


A project with clearly defined outcomes and phases, little to no
volatility, and well-knowntechnologies would be a good candidate for
which project management method? correct answer Traditional

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
starwid Yale University
View profile
Follow You need to be logged in order to follow users or courses
Sold
13
Member since
6 months
Number of followers
1
Documents
8058
Last sold
4 days ago

3.3

4 reviews

5
1
4
0
3
2
2
1
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions