Questions and CORRECT Answers
Job Site Posting - CORRECT ANSWER - 1: OSHA Regulations
2: Department Of Labor Postings
3: Accident Prevention Postings
4: Safety Plan
5: Accident Reports
6: EEO Poster
7: Job Safety and Health Protection Plan
8: Criminal Code Notice
Inspector Responsibilities Do's - CORRECT ANSWER - 1: Report to EIC
2: Record Measurement, complete reports, communicate quantities to contractor
3: Keep Track of Time and Attendance
4: Inspection Reports, Material Registers
Inspector Responsibilities Dont's - CORRECT ANSWER - 1: Cannot Make subjective
interpretations of plans
2: Cannot order work, including provided in construction documents
What grade Bar should be used for structures - CORRECT ANSWER - Grade 60
What coated bar should be used for concrete structures? - CORRECT ANSWER - Zinc or
Epoxy coated
Types of Placement Machines - CORRECT ANSWER - 1: Bucket Hoppers
2: Manuel, Motor Propelled
, 3: Chutes and Drop Chutes
4: Tremies
5: pumps
Where should concrete be placed on a slope - CORRECT ANSWER - At the bottom
How far should reinforcing steel be placed away from forms? - CORRECT ANSWER -3
inches
Where should reinforcing steel tie wire be faced? - CORRECT ANSWER - Away from the
finished surface
Pay Weight for Reinforcing Steel - CORRECT ANSWER - D² X L ÷ 162.198
How do you pay for Reinforcing Steel - CORRECT ANSWER - Weight of Bar x Linear
foot of Bar
What is Type A Soil identification? - CORRECT ANSWER - compressive strength of 1.5
TSF per Sq FT
Clay: Plasticity Index 17% Cohesive <0.002
Clay Loam: Mixture of silt,sand and clay, 40,40,20
What is Type B soil Identification? - CORRECT ANSWER - Compressive strength of 0.5
TSF but less than 1.5TSF
Angular Gravel
Silt
Silt Loam