INSPECTOR EXAM
ANSWER ALL QUESTIONS IN THIS SECTION
QUESTION 1
DEQ is responsible for enforcing the ______ while locality _______ are
responsible for enforcing local ordinances. - ANSWERS-Construction GP, VSMP
QUESTION 2
BMPs use these three mechanisms to control pollution: - ANSWERS-Infiltration,
settling, and vegetative uptake
QUESTION 3
How long does a locality VSMP authority have to determine the completeness of a
SWM plan? - ANSWERS-15 days
END OF
PAGE
1
, VA DEQ SWM LATEST
INSPECTOR EXAM
QUESTION 4
Every year, the locality VSMP must submit information to DEQ. When is this due,
and what info must be provided? - ANSWERS-Due by Oct. 1, and must include:
new types of SWM facilities, geographic coordinates of them, acres treated, and
surface waters/karst features into which they discharge.
QUESTION 5
A locality VSMP must be at least as stringent as what state permit? - ANSWERS-
The construction GP
QUESTION 6
What is the maximum penalty that may be imposed under the stormwater
management act? - ANSWERS-$32,500
QUESTION 7
How long must a VSMP authority retain a registration statement? - ANSWERS-At
least three years after project completion or state permit termination.
END OF
PAGE
2