UDC was required at time of installation for all systems installed after?
| | | | | | | | | | |
January 1, 2000 | |
July 1, 2005, service techs shall possess or work under someone who has a current
| | | | | | | | | | | | | |
certification indicating he or she has passed the?
| | | | | | | |
ICC UST Service Technician Exam
| | | |
ICC cert must be renewed every?
| | | | |
24 months
|
Service techs must possess or be employed by a person who has the appropriate
| | | | | | | | | | | | |
contractor's license unless?
| | |
The individual has a tank testing license
| | | | | |
Service tech is defined by any individual who?
| | | | | | |
Tests UST monitoring equipment, trouble shoots UST systems, and/or
| | | | | | | |
installs UST monitoring equipment.
| | | |
If the manufacturer training no longer exist, the local agency may?
| | | | | | | | | |
Approve comparable alternate training . | | | |
UST includes? |
Tank and connected piping
| | |
,What is considered a UST?
| | | |
A petroleum storage tank.
| | |
What UST system meets the requirements for secondary containment?
| | | | | | | |
Doubled wall tanks | |
According to title 23; the following piping components if installed after July 1, 1987
| | | | | | | | | | | | |
must have secondary containment.
| | | |
Pressured product piping | |
Considered "pipe" on tanks installed after July 1, 2003. | | | | | | | |
Pressured product piping and below ground vapor recovery.
| | | | | | | |
Under dispenser containment (UDC) was required for all existing UST
| | | | | | | | |
systems by
| |
December 31, 2003 | |
System for exchanging gas vapors in a storage tank and product in a fuel delivery
| | | | | | | | | | | | | |
truck
|
Stage 1 vapor recovery | | |
An approved method for non-visual monitoring for existing UST systems. Statistical
| | | | | | | | | |
Inventory Reconciliation (SIR)
| | |
ATG must be capable for detecting a release of?
| | | | | | | |
0.2 gallons per hour
| | |
,What is no longer an approved method for non-visual monitoring on existing UST
| | | | | | | | | | | |
systems?
|
Manual inventory reconciliation.| |
Automatic line leak detectors installed on underground piping with secondary
| | | | | | | | |
containment shall be capable of detecting a leak of ?
| | | | | | | | | |
3 gallons per hour at 10 psi
| | | | | |
How often should ATG be programmed to test the tank?
| | | | | | | | |
At least monthly
| |
According to PEI RP 300, a combustible gas can be used to?
| | | | | | | | | | |
Detect vapor leaks in a vapor recovery system.
| | | | | | |
According to PEI RP 300, a written scope of work for vapor recovery installation
| | | | | | | | | | | | |
should include?
| |
Construction plans |
Positive shut off overfill protection device must stop the flow of fuel when the tank is
| | | | | | | | | | | | | | |
no more then?
| | |
95% full |
According to Executive Order (EO) VR 201-A , what could cause a nozzle shut off
| | | | | | | | | | | | | |
mechanism or malfunction?
| | |
Depended filter seal damage | | |
According to VR 201-A, breakaway reconnection must be?
| | | | | | |
Logged in GDF log | | |
, According to PEI RP 300 what is an INCORRECT method of documenting piping
| | | | | | | | | | | |
location?
|
Sketching a diagram on the inside cover of vapor recovery equipment manual
| | | | | | | | | | |
According to PEI RP 300 as built drawing or pictures of the underground pipping
| | | | | | | | | | | | |
and other components shall be
| | .| | |
maintained as long as UST is in service. | | | | | | |
According to EO VR 101-E maintenance records are required to include what?
| | | | | | | | | | |
Name and Designated UST Operator.
| | | |
The Phil-Tite EVR Phase 1 system require that vapor vent pipes at any UST system
| | | | | | | | | | | | | |
be
|
Used with no more than 3 p/v valves
| | | | | | |
According to EO VR 2010 after installing a new spout assembly in the Healy 900
| | | | | | | | | | | | | |
nozzle the following test must be conducted?
| | | | | | |
Nozzle dispensing shut off test | | | |
According to Healy EO VR 201-A a vapor recovery record is to be maintained by?
| | | | | | | | | | | | | |
Gasoline dispensing facility operator(GDF) | | |
An enhanced leak detection test is required within how many feet of a public
| | | | | | | | | | | | |
drinking well?
| |
1000 feet |
What are the components of the Fire Triangle?
| | | | | | |
Certification Exam Study Guide Questions
With Correct Answers
Terms in this set (278) | | | |
Original
UDC was required at time of installation for all systems installed after?
| | | | | | | | | | |
January 1, 2000 | |
July 1, 2005, service techs shall possess or work under someone who has a current
| | | | | | | | | | | | | |
certification indicating he or she has passed the?
| | | | | | | |
ICC UST Service Technician Exam
| | | |
ICC cert must be renewed every?
| | | | |
24 months
|
Service techs must possess or be employed by a person who has the appropriate
| | | | | | | | | | | | |
contractor's license unless?
| | |
The individual has a tank testing license
| | | | | |
Service tech is defined by any individual who?
| | | | | | |
Tests UST monitoring equipment, trouble shoots UST systems, and/or
| | | | | | | |
installs UST monitoring equipment.
| | | |
If the manufacturer training no longer exist, the local agency may?
| | | | | | | | | |
Approve comparable alternate training . | | | |
UST includes? |
Tank and connected piping
| | |
,What is considered a UST?
| | | |
A petroleum storage tank.
| | |
What UST system meets the requirements for secondary containment?
| | | | | | | |
Doubled wall tanks | |
According to title 23; the following piping components if installed after July 1, 1987
| | | | | | | | | | | | |
must have secondary containment.
| | | |
Pressured product piping | |
Considered "pipe" on tanks installed after July 1, 2003. | | | | | | | |
Pressured product piping and below ground vapor recovery.
| | | | | | | |
Under dispenser containment (UDC) was required for all existing UST
| | | | | | | | |
systems by
| |
December 31, 2003 | |
System for exchanging gas vapors in a storage tank and product in a fuel delivery
| | | | | | | | | | | | | |
truck
|
Stage 1 vapor recovery | | |
An approved method for non-visual monitoring for existing UST systems. Statistical
| | | | | | | | | |
Inventory Reconciliation (SIR)
| | |
ATG must be capable for detecting a release of?
| | | | | | | |
0.2 gallons per hour
| | |
,What is no longer an approved method for non-visual monitoring on existing UST
| | | | | | | | | | | |
systems?
|
Manual inventory reconciliation.| |
Automatic line leak detectors installed on underground piping with secondary
| | | | | | | | |
containment shall be capable of detecting a leak of ?
| | | | | | | | | |
3 gallons per hour at 10 psi
| | | | | |
How often should ATG be programmed to test the tank?
| | | | | | | | |
At least monthly
| |
According to PEI RP 300, a combustible gas can be used to?
| | | | | | | | | | |
Detect vapor leaks in a vapor recovery system.
| | | | | | |
According to PEI RP 300, a written scope of work for vapor recovery installation
| | | | | | | | | | | | |
should include?
| |
Construction plans |
Positive shut off overfill protection device must stop the flow of fuel when the tank is
| | | | | | | | | | | | | | |
no more then?
| | |
95% full |
According to Executive Order (EO) VR 201-A , what could cause a nozzle shut off
| | | | | | | | | | | | | |
mechanism or malfunction?
| | |
Depended filter seal damage | | |
According to VR 201-A, breakaway reconnection must be?
| | | | | | |
Logged in GDF log | | |
, According to PEI RP 300 what is an INCORRECT method of documenting piping
| | | | | | | | | | | |
location?
|
Sketching a diagram on the inside cover of vapor recovery equipment manual
| | | | | | | | | | |
According to PEI RP 300 as built drawing or pictures of the underground pipping
| | | | | | | | | | | | |
and other components shall be
| | .| | |
maintained as long as UST is in service. | | | | | | |
According to EO VR 101-E maintenance records are required to include what?
| | | | | | | | | | |
Name and Designated UST Operator.
| | | |
The Phil-Tite EVR Phase 1 system require that vapor vent pipes at any UST system
| | | | | | | | | | | | | |
be
|
Used with no more than 3 p/v valves
| | | | | | |
According to EO VR 2010 after installing a new spout assembly in the Healy 900
| | | | | | | | | | | | | |
nozzle the following test must be conducted?
| | | | | | |
Nozzle dispensing shut off test | | | |
According to Healy EO VR 201-A a vapor recovery record is to be maintained by?
| | | | | | | | | | | | | |
Gasoline dispensing facility operator(GDF) | | |
An enhanced leak detection test is required within how many feet of a public
| | | | | | | | | | | | |
drinking well?
| |
1000 feet |
What are the components of the Fire Triangle?
| | | | | | |