Graded A+
Which of these is the correct order of the 7-step construction project initiation process that was
discussed in the class?
-Prepare the Bid Package, Advertise for Bids, Manage the Bid Cycle, Bid Opening, Bid Award,
Sign Agreement, Notice to Proceed
-Prepare the Bid Package, Bid Opening, Manage the Bid Cycle, Advertise for Bids, Bid Award,
Sign Agreement, Notice to Proceed
-Prepare the Bid Package, Advertise for Bids, Manage the Bid Cycle, Bid Award, Preconstruction
Meeting, Sign Agreement, Notice to Proceed
-Advertise for Bids, Prepare the Bid Package, Manage the Bid Cycle, Bid Award, Sign
Agreement, Preconstruction Meeting, Notice to Proceed Prepare the Bid Package,
Advertise for Bids, Manage the Bid Cycle, Bid Opening, Bid Award, Sign Agreement, Notice to
Proceed
, True/ False
The Agency CM is responsible for directing the Contractor's means and methods. False
Which of the following is a cost associated with mobilization?
-Cost of performing excavation
-Cost of performing punch list work
-Cost of delivering equipment, materials, and labor to the site
-Contractor Quality Control (CQC) inspections Cost of delivering equipment, materials,
and labor to the site
What term refers to the allocation of markup (overhead and profit) to the schedule of values
items that will be completed early in the project?
-Bid balancing