100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

DBIA - Project Delivery Questions and Answers 100% Correct

Rating
-
Sold
-
Pages
2
Grade
A+
Uploaded on
21-05-2025
Written in
2024/2025

DBIA - Project Delivery Questions and Answers 100% Correct

Institution
DBIA
Course
DBIA








Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
DBIA
Course
DBIA

Document information

Uploaded on
May 21, 2025
Number of pages
2
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

DBIA - Project Delivery Questions and
Answers 100% Correct
Bridging is the passing off or assigning of an architect's partially designed drawings to
another architect or DB Firm. T/F? - ANSWER-True

CM @ Risk project delivery is faster than Design-Bid-Build, but can be slower than
Design-Build. T/F - ANSWER-True

CM-as-Advisor may be added to any project delivery method. T/F? - ANSWER-True

Design - Build delivers equal or higher quality than DBB projects according to a
comparative study by CII and Penn State. T/F? - ANSWER-True

Fast tracking a project and phased construction is possible using the CM @ Risk project
delivery method. t/f? - ANSWER-true

In a GMP contract approach/payment the Owner and DB entity share the costs in
excess of the GMP established by the DB entity. T/F? - ANSWER-False

It is recommended to get a contractor on board early during the business and planning
stage of a DB project to have the best opportunity to achieve all objectives. T/F -
ANSWER-True

Most Public Procurement statutes require the selection of design services be purchased
on the basis of lowest responsible bid? T/F? - ANSWER-False

Project delivery selection influences when contractor gets on board. T/F - ANSWER-
True

The DB delivery method may include additional services such as site acquisition and
financing. T/F? - ANSWER-True

The owner can pre-determine how a project's construction team will interact with him or
her and with each other through the selection of the delivery system. T/F? - ANSWER-
True

The primary goal in choosing a delivery method is to ensure that it will meet the Owner's
project objectives while at the same time allowing the project to be completed on time
and within budget? T/F - ANSWER-True

There are always at least three parties involved in every project delivery process; the
Owner, Architect and Contractor. T/F? - ANSWER-True

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
CLOUND Exam
View profile
Follow You need to be logged in order to follow users or courses
Sold
601
Member since
2 year
Number of followers
389
Documents
10875
Last sold
5 days ago
PROF MM

HELLO WELCOME TO THIS PAGE WHERE YOU WILL FIND ALL EXAMS ,STUDY GUIDE ,CASE, TESTBANKS AND ANY OTHER STUDY MATERIALS,

3.9

116 reviews

5
58
4
16
3
29
2
3
1
10

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions