Pamela is creating a form to collect requests for her marketing
creative services team. In order to complete any request, she
needs to know which cost center to bill for the work. How can
she ensure that each request will contain the cost center? -
ANSWER-Make the field required
Which column records when a form was submitted? -
ANSWER-Created (Date)
What is the most efficient way to change the order that fields are
displayed on a form? - ANSWER-Drag-and-drop the fields on
the form builder
Which setting must you enable to automatically track who
makes form submissions? - ANSWER-Require people to log in
to Smartsheet
,2|Page
Sergei has a sheet with a form to collect requests for his IT team.
He wants every new submission to be assigned a Status of Not
Started. What is the recommended way for him to accomplish
this? - ANSWER-Assign a default value of Not Started and hide
the Status field
Which column type can be displayed on a form as radio buttons?
- ANSWER-Dropdown (Single Select)
Reginald is managing requests for his IT team using a sheet with
a form. Employees can request the completion date in the "Date
Need By" column. The team member assigned to the work
enters a date in the "Estimated Completion Date" column.He
wrote a formula to show if requests are on track. The formula
will display On Time or the number of days late. The formula
displays an error, #UNPARSEABLE.
Reginald's formula:=IF(([Estimated Completion Date]1 - [Date
Need By]1) = 0, On Time, ([Estimated Completion Date]1 -
[Date Need By]1))
Which section of the formula does Reginald need to correct? -
ANSWER-The value if true
Tricia has a task sheet where she is tracking both % Complete
and Status. Which function can she use to change the symbol in
, 3|Page
the Status column based on the value in the % Complete
column? - ANSWER-IF()
Which function can you use to add up numerical values? -
ANSWER-SUM()
Guillermo owns a project tracking sheet. His sheet uses a
hierarchy with all tasks being children of a phase. He created a
filter to help his team see only their tasks. They are reporting
that it is difficult to understand the phase as there are tasks with
the same name in multiple phases. To help them understand the
phase, he has added a column titled "Phase." What function can
he combine with JOIN() to show this information? - ANSWER-
ANCESTORS()
John wants to have his health column display a red symbol if a
task is past its due date. Which formula can he use? - ANSWER-
=IF([Due Date]@row < TODAY(), "Red")
What level of hierarchy should the CHILDREN() function be