400 scf of LPG equals - ANS-@ 47lbs
Additional hearth watch on floors underneath required whilst - ANS-Work is being executed near
fringe of unenclosed floor or near ground commencing
Building owner must be notified xxhrs before hot work - ANS-48hrs
City huge allow - ANS--Valid to temp save, deal with, use and sell risky substances metropolis
huge as long as activity does not exceed 30day and dangerous substances are removed at the
give up of each work day.
- have to not exceed five gal fuel, 250gal other flammable liquid and 300gal of combustible
liquid
CNG - ANS-Compressed natural gas
CNG containers should no longer exceed xxxscf - ANS-381scf
CNG of xxx scf won't be saved, handled or used indoor/roof - ANS-eight.7scf
CoF required for heat applied roof gadget - ANS-G60, G41 or G42
CoF required for oxy/gasoline tour has operation - ANS-G60
CoF required whilst fireplace Gaurd is needed - ANS-F60
FC chapter 26 - ANS-Welding and other hot work
FDNY allow required - ANS--Storage, use or dealing with oxygen and a flammable gasoline
- garage, use or coping with of flammable gas (LP,CNG) over four hundred scf
- garage, use or managing of oxygen over 504scf
Fire extinguisher have to be with in - ANS-30ft of place no much less than 1 extinguisher
Fire watch - ANS-Must be maintained during hot work operations
Fire watch need to check out when LPG/CNG is used - ANS-30min and the 1 hr after final touch
fireplace watch must signal report
Fire watch must continue to be for at least xx min after work is completed - ANS-30min