SAFe | Advanced Scrum Master Practice Test
(4.6) | Exam Questions And Answers
`Which statement is true about the phase-gate milestone model
and risk reduction? -
correct answer ✅--- camila answer: A*
A. It does not mitigate risk as intended
B. It creates large batches of requirements
C. It reduces product increment values
D. It helps to visualize and limit WIP
--
https://www.scaledagileframework.com/base-milestones-on-
objective-evaluation-of-working-systems/
`When does the Inspect and Adapt event happen? -
correct answer ✅--- camila answer: D
A. At the end of the System Demo
B. At the end of every two weeks
C. At the end of the second day of PI Planning
D. At the end of each PI
--
,SAFe | Advanced Scrum Master Practice Test
(4.6) | Exam Questions And Answers
https://www.scaledagileframework.com/inspect-and-adapt/
`Who reviews the top capabilities for the upcoming PI? -
correct answer ✅--- camila answer: C*
A. Project Manager
B. Solution Architect/Engineer
C. Solution Management
D. Project Owner
--
https://www.scaledagileframework.com/product-and-solution-
management/
`Why should team members continuously and actively engage with
other teams during PI Planning? -
correct answer ✅--- camila answer: C or A5'
-C
--A
A.To manage dependencies and resolve impediments
,SAFe | Advanced Scrum Master Practice Test
(4.6) | Exam Questions And Answers
B. To understand how the other team is working
C. To foster an environment of capacity and velocity
D. To create a backlog of features the team can adopt
--
https://www.scaledagileframework.com/pi-planning/
`What are two Release Train Engineer responsibilities? (Choose
two.) -
correct answer ✅--- camila answer: A & C*
A. Facilitate PI Planning readiness and the event itself
B. Understand Customer needs; validate solutions
C. Drive relentless improvement through Inspect and Adapt
D. Build an effective Product Owner / Product Manager team
, SAFe | Advanced Scrum Master Practice Test
(4.6) | Exam Questions And Answers
E. Manage and prioritize the flow of work to the program
--
https://www.scaledagileframework.com/release-train-engineer-
and-solution-train-engineer/
`What anti-pattern can emerge during the Scrum of Scrums? -
correct answer ✅--- camila answer: D*
A. Scrum Masters bring in risks and impediments for escalation
B. Scrum Masters work with the Release Train Engineer to resolve
risks and impediments
C. Scrum Masters have a daily 15 minute meet-after with the
Release Train Engineer
D. Scrum Masters report on the teams' task status each day
--
(4.6) | Exam Questions And Answers
`Which statement is true about the phase-gate milestone model
and risk reduction? -
correct answer ✅--- camila answer: A*
A. It does not mitigate risk as intended
B. It creates large batches of requirements
C. It reduces product increment values
D. It helps to visualize and limit WIP
--
https://www.scaledagileframework.com/base-milestones-on-
objective-evaluation-of-working-systems/
`When does the Inspect and Adapt event happen? -
correct answer ✅--- camila answer: D
A. At the end of the System Demo
B. At the end of every two weeks
C. At the end of the second day of PI Planning
D. At the end of each PI
--
,SAFe | Advanced Scrum Master Practice Test
(4.6) | Exam Questions And Answers
https://www.scaledagileframework.com/inspect-and-adapt/
`Who reviews the top capabilities for the upcoming PI? -
correct answer ✅--- camila answer: C*
A. Project Manager
B. Solution Architect/Engineer
C. Solution Management
D. Project Owner
--
https://www.scaledagileframework.com/product-and-solution-
management/
`Why should team members continuously and actively engage with
other teams during PI Planning? -
correct answer ✅--- camila answer: C or A5'
-C
--A
A.To manage dependencies and resolve impediments
,SAFe | Advanced Scrum Master Practice Test
(4.6) | Exam Questions And Answers
B. To understand how the other team is working
C. To foster an environment of capacity and velocity
D. To create a backlog of features the team can adopt
--
https://www.scaledagileframework.com/pi-planning/
`What are two Release Train Engineer responsibilities? (Choose
two.) -
correct answer ✅--- camila answer: A & C*
A. Facilitate PI Planning readiness and the event itself
B. Understand Customer needs; validate solutions
C. Drive relentless improvement through Inspect and Adapt
D. Build an effective Product Owner / Product Manager team
, SAFe | Advanced Scrum Master Practice Test
(4.6) | Exam Questions And Answers
E. Manage and prioritize the flow of work to the program
--
https://www.scaledagileframework.com/release-train-engineer-
and-solution-train-engineer/
`What anti-pattern can emerge during the Scrum of Scrums? -
correct answer ✅--- camila answer: D*
A. Scrum Masters bring in risks and impediments for escalation
B. Scrum Masters work with the Release Train Engineer to resolve
risks and impediments
C. Scrum Masters have a daily 15 minute meet-after with the
Release Train Engineer
D. Scrum Masters report on the teams' task status each day
--