Purpose of scheduling - ✔✔to determine:
- project duration
- critical activities (paths)
- early start schedule
- late start schedule
bar chart (gantt chart) characteristics - ✔✔- horizontal bar chart
- illustrate start and finish of activities
- dependency between activities is typically not shown
- easy to show current schedule status or % complete
- length of bar corresponds to activity duration
bar chart advantages - ✔✔- easy to present project tasks, their durations, and
anticipated start and finish dates
- no special knowledge needed to determine status of project
- suitable for small/simple projects