COSC-475 Scheduling Terms Exam 2025 Questions and Answers 100% Pass Activity/Task - Smaller components included in an overall schedule that are identified for the purpose of planning, scheduling, monitoring, and controlling the project. Activities are described in terms of time and will consume resources. Milestone - Mark a significant point in time for reference or measurement, zero duration, just a goal date. Work Breakdown Structure (WBS) - A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. Duration - The length of time for an activity, series of activities or even a project. Durations are always in work days. Predecessor - Task that comes before another task and is dependent on the following task. Successor - Task that comes after another task and is dependent on the previous task. Lag Time - Planned delay between tasks. Relationship - Defines how an activity relates to the start or finish of another activity. Add relationships between activities to create a path through your schedule 2COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED External Relationship - Finish to Start (FS) Finish to Finish (FF) Start to Start (SS) Start to Finish (SF) Critical Path - Longest path to complete the project. Longest continuous chain of activities through the network schedule which establishes the minimum overall project duration. Baseline Plan - Original Schedule Progress - Actual completion status of a task in the schedule. Resource Calendar - A calendar which indicates the working days of a specific resource. People, equipment, or materials. Summary Task - A single-line task that summarizes all the tasks indicated within its group. Usually shown to indicate the total duration of a phase. Slack - The time a task can be delayed without affecting the interdependent tasks dates. Slippage - The duration of time that a task varies from the original baseline plan. Generally, it indicates a delay from the original baseline Start Date. Variance - The measure of change in a task duration either

Show more Read less
Institution
COSC 475
Course
COSC 475









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
COSC 475
Course
COSC 475

Document information

Uploaded on
April 29, 2025
Number of pages
6
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

COSC-475 Scheduling Terms Exam 2025
Questions and Answers 100% Pass


Activity/Task - ✔✔Smaller components included in an overall schedule that are
identified for the purpose of planning, scheduling, monitoring, and controlling the
project. Activities are described in terms of time and will consume resources.

Milestone - ✔✔Mark a significant point in time for reference or measurement, zero
duration, just a goal date.

Work Breakdown Structure (WBS) - ✔✔A hierarchical decomposition of the total scope
of work to be carried out by the project team to accomplish the project objectives and
create the required deliverables.

Duration - ✔✔The length of time for an activity, series of activities or even a project.
Durations are always in work days.

Predecessor - ✔✔Task that comes before another task and is dependent on the
following task.

Successor - ✔✔Task that comes after another task and is dependent on the previous
task.

Lag Time - ✔✔Planned delay between tasks.

Relationship - ✔✔Defines how an activity relates to the start or finish of another
activity. Add relationships between activities to create a path through your schedule



COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED 1

, External Relationship - ✔✔Finish to Start (FS)

Finish to Finish (FF)

Start to Start (SS)

Start to Finish (SF)

Critical Path - ✔✔Longest path to complete the project. Longest continuous chain of
activities through the network schedule which establishes the minimum overall project
duration.

Baseline Plan - ✔✔Original Schedule

Progress - ✔✔Actual completion status of a task in the schedule.

Resource Calendar - ✔✔A calendar which indicates the working days of a specific
resource. People, equipment, or materials.

Summary Task - ✔✔A single-line task that summarizes all the tasks indicated within its
group. Usually shown to indicate the total duration of a phase.

Slack - ✔✔The time a task can be delayed without affecting the interdependent tasks
dates.

Slippage - ✔✔The duration of time that a task varies from the original baseline plan.
Generally, it indicates a delay

from the original baseline Start Date.

Variance - ✔✔The measure of change in a task duration either in a positive or negative
connotation.

Free Float - ✔✔The amount of time that a task can slip before it impacts the start of the
successor task. The amount




COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED 2

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
OliviaWest Teachme2-tutor
View profile
Follow You need to be logged in order to follow users or courses
Sold
109
Member since
1 year
Number of followers
17
Documents
8528
Last sold
1 week ago
Pure Orchid Haven.

All Documents,and package deals offered by seller Olivia West.

2.8

22 reviews

5
6
4
2
3
4
2
1
1
9

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions