100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

COSC 475 Scheduling Terms Exam 2025 Questions and Answers 100% Pass

Rating
-
Sold
-
Pages
7
Grade
A+
Uploaded on
29-04-2025
Written in
2024/2025

COSC 475 Scheduling Terms Exam 2025 Questions and Answers 100% Pass Activity / Task - Used in Primavera P6 scheduling software, the overall schedule includes smaller components identified for planning, scheduling, monitoring, and controlling the project. Activities are described in terms of time and will generally consume resources Task - Used in Microsoft Project scheduling software, the overall schedule includes smaller components identified for planning, scheduling, monitoring, and controlling the project. Activities are described in terms of time and will generally consume resources Milestones - They mark a significant point in time for reference or measurement. They have a zero duration. Often, a goal date. Work Breakdown Structure - The master Work Breakdown Structure is a hierarchy of work that must be completed within the project and groups activities into various phases (ex, Preconstruction, Foundation, Structure, Finishes, Close-out, etc.). Duration - The length of time for an activity, series of activities, or a project. As the schedule software reports, durations are always workdays, not calendar days. Predecessor - A task that comes before another task, and its completion depends upon the start of the following task. 2COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED Successor - A task that comes after another and depends on the previous task. Lag time - Planned delay between tasks. This is the same as Slack Relationships - define how an activity relates to the start or finish of another activity or assignment. Add relationships between activities to create a path through your schedule from the first activity to the last activity. These relationships, which form the logic of the project network, are used together with activity durations to determine schedule dates. An activity can have as many relationships as necessary to model the work that must be done. You can also identify relationships between activities in different projects; this type of relationship is referred to as an external relationship. Types of relationships are shown below: a. Finish to Start relationship (FS) b. Finish to Finish relationship (FF) c. Start to Start relationship (SS) d. Start-to-finish relationship. (SF) Note: This is the least frequently used relationship because it is counterintuitive. Critical Path - The longest path to completion of the project is the longest continuous chain of activities through the network schedule, which establishes the minimum overall project duration. Baseline Plan - Original schdeule Progress - Actual completion status of a task in the schedule Resource Calendar - A calendar that indicates the working

Show more Read less
Institution
COSC 475
Course
COSC 475









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
COSC 475
Course
COSC 475

Document information

Uploaded on
April 29, 2025
Number of pages
7
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

COSC 475 Scheduling Terms Exam 2025
Questions and Answers 100% Pass


Activity / Task - ✔✔Used in Primavera P6 scheduling software, the overall schedule
includes smaller components identified for planning, scheduling, monitoring, and
controlling the project. Activities are described in terms of time and will generally
consume resources

Task - ✔✔Used in Microsoft Project scheduling software, the overall schedule includes
smaller components identified for planning, scheduling, monitoring, and controlling
the project. Activities are described in terms of time and will generally consume
resources

Milestones - ✔✔They mark a significant point in time for reference or measurement.
They have a zero duration. Often, a goal date.

Work Breakdown Structure - ✔✔The master Work Breakdown Structure is a hierarchy
of work that must be completed within the project and groups activities into various
phases (ex, Preconstruction, Foundation, Structure, Finishes, Close-out, etc.).

Duration - ✔✔The length of time for an activity, series of activities, or a project. As the
schedule software reports, durations are always workdays, not calendar days.

Predecessor - ✔✔A task that comes before another task, and its completion depends
upon the start of the following task.




COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED 1

, Successor - ✔✔A task that comes after another and depends on the previous task.

Lag time - ✔✔Planned delay between tasks. This is the same as Slack

Relationships - ✔✔define how an activity relates to the start or finish of another activity
or assignment. Add relationships between activities to create a path through your
schedule from the first activity to the last activity. These relationships, which form the
logic of the project network, are used together with activity durations to determine
schedule dates. An activity can have as many relationships as necessary to model the
work that must be done. You can also identify relationships between activities in
different projects; this type of relationship is referred to as an external relationship.
Types of relationships are shown below: a. Finish to Start relationship (FS)

b. Finish to Finish relationship (FF)

c. Start to Start relationship (SS)

d. Start-to-finish relationship. (SF)

Note: This is the least frequently used relationship because it is counterintuitive.

Critical Path - ✔✔The longest path to completion of the project is the longest continuous
chain of activities through the network schedule, which establishes the minimum
overall project duration.

Baseline Plan - ✔✔Original schdeule

Progress - ✔✔Actual completion status of a task in the schedule

Resource Calendar - ✔✔A calendar that indicates the working days of a specific
resource, such as people, equipment, or materials.

Summary Task - ✔✔A single-line task that summarizes all the tasks indicated within its
group. Usually shown to indicate the total duration of a phase




COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED 2

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
OliviaWest Teachme2-tutor
View profile
Follow You need to be logged in order to follow users or courses
Sold
109
Member since
1 year
Number of followers
17
Documents
8528
Last sold
1 week ago
Pure Orchid Haven.

All Documents,and package deals offered by seller Olivia West.

2.8

22 reviews

5
6
4
2
3
4
2
1
1
9

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions