100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

COSC 475 Scheduling Terms and Definitions Exam 2025 Questions and Answers 100% Pass

Rating
-
Sold
-
Pages
5
Grade
A+
Uploaded on
29-04-2025
Written in
2024/2025

COSC 475 Scheduling Terms and Definitions Exam 2025 Questions and Answers 100% Pass Activity/Task - Smaller components included in an overall schedule that are identified for the purpose of planning, scheduling, monitoring, and controlling the project. Activities are described in terms of time and will they generally consume resources. Milestone - They mark a significant point in time for reference or measurement. They have a zero duration. Often, a goal date. Work Breakdown Structure - The master Work Breakdown Structure is a hierarchy of work that must be completed within the project and groups activities into various phases (ex: Preconstruction, Foundation, Structure, Finishes, Close-out, etc). Duration - The length of time for an activity, series of activities, or a project. Reported in schedule software, durations are always in work days not calendar days. Predecessor - A task that comes before another task and its completion is dependent upon the following task's start. Successor - A task that comes after another task and is dependent upon the previous task. 2COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED Lag time - Planned delay between tasks. Relationship - defines how an activity relates to the start or finish of another activity or assignment. Add relationships between activities to create a path through your schedule from the first activity to the last activity. These relationships, which form the logic of the project network, are used together with activity durations to determine schedule dates. An activity can have as many relationships as necessary to model the work that must be done. You can also identify relationships between activities that are in different projects; this type of relationship is referred to as an external relationship. Types of relationships are shown below: a. Finish to Start relationship (FS) b. Finish to Finish relationship (FF) c. Start to Start relationship (SS) d. Start to Finish relationship. (SF) Note:

Show more Read less
Institution
COSC 475
Course
COSC 475









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
COSC 475
Course
COSC 475

Document information

Uploaded on
April 29, 2025
Number of pages
5
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

COSC 475 Scheduling Terms and
Definitions Exam 2025 Questions
and Answers 100% Pass


Activity/Task - ✔✔Smaller components included in an overall schedule that are
identified for the purpose of planning, scheduling, monitoring, and controlling the
project. Activities are described in terms of time and will they generally consume
resources.

Milestone - ✔✔They mark a significant point in time for reference or measurement.
They have a zero duration. Often, a goal date.

Work Breakdown Structure - ✔✔The master Work Breakdown Structure is a hierarchy
of work that must be completed within the project and groups activities into various
phases (ex: Preconstruction, Foundation, Structure, Finishes, Close-out, etc).

Duration - ✔✔The length of time for an activity, series of activities, or a project.
Reported in schedule software, durations are always in work days not calendar days.

Predecessor - ✔✔A task that comes before another task and its completion is dependent
upon the following task's start.

Successor - ✔✔A task that comes after another task and is dependent upon the previous
task.



COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED 1

, Lag time - ✔✔Planned delay between tasks.

Relationship - ✔✔defines how an activity relates to the start or finish of another activity
or assignment. Add relationships between activities to create a path through your
schedule from the first activity to the last activity. These relationships, which form the
logic of the project network, are used together with activity durations to determine
schedule dates. An activity can have as many relationships as necessary to model the
work that must be done. You can also identify relationships between activities that are
in different projects; this type of relationship is referred to as an external relationship.
Types of relationships are shown below:

a. Finish to Start relationship (FS)

b. Finish to Finish relationship (FF)

c. Start to Start relationship (SS)

d. Start to Finish relationship. (SF) Note: this is the least seldom used since it is
counterintuitive.

Critical Path - ✔✔Longest path to complete the project. The longest continuous chain of
activities through the network schedule which establishes the minimum overall project
duration.

Baseline Plan - ✔✔Original Schedule

Progress - ✔✔Actual completion status of a task in the schedule.

Resource Calendar - ✔✔A calendar which indicates the working days of a specific
resource. Resources can be people, equipment, or materials.

Summary Task - ✔✔A single line task which summarizes all the tasks indicated within
its group. Usually shown to indicate the total duration of a phase.




COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED 2

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
OliviaWest Teachme2-tutor
View profile
Follow You need to be logged in order to follow users or courses
Sold
109
Member since
1 year
Number of followers
17
Documents
8528
Last sold
1 week ago
Pure Orchid Haven.

All Documents,and package deals offered by seller Olivia West.

2.8

22 reviews

5
6
4
2
3
4
2
1
1
9

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions