1. Who performs a structural observation?
A) the RDP in responsible charge
B) The special inspector
C) The contractor
D) The building official
Answer> A) the RDP in responsible charge
2. Who prepares the statement of special inspections?
A) The building offficial
B) The contractor
C) The owner
1/7
, D) The RDP
Answer> D) The RDP
3. Who is in charge of reviewing and approving reports?
A) The building offficial
B) The contractor
C) The owner
D) The RDP
Answer> D) The RDP
4. ICC exams are based on which document?
a) ACI
b) IBC
c) ASTM
Answer> B) IBC
5. Who is in charge of giving "approval to proceed"
A) The building offficial
B) The contractor