and CORRECT Answers
civil plans - CORRECT ANSWER - Plans used for work that has to do with construction
in or on the earth are called______plans
RFI - CORRECT ANSWER - to clarify any discrepancies in the plans, use an_________
title block - CORRECT ANSWER - Information about the structure or assembly is
provided in the ________
sheet title - CORRECT ANSWER - The project is identified by the__________
engineers - CORRECT ANSWER - Site plans are developed using a________scale
triangular - CORRECT ANSWER - The_______Form of an architect's scale is commonly
used because it contains a variety of scales
Alphabet of lines - CORRECT ANSWER - The lines commonly used on a blueprint are
sometimes called the________________
Arrows - CORRECT ANSWER - Dimension lines end with a
Title sheet - CORRECT ANSWER - The symbols used for each type of plan should be
indicated on the_________________
square or circle - CORRECT ANSWER - A keynote is a number or letter that is often used
instead of symbols and usually appears in_____________