100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.6 TrustPilot
logo-home
Exam (elaborations)

Cosc 475 Final ACTUAL UPDATED Exam Questions and CORRECT Answers

Rating
-
Sold
-
Pages
11
Grade
A+
Uploaded on
27-04-2025
Written in
2024/2025

Cosc 475 Final ACTUAL UPDATED Exam Questions and CORRECT Answers crtical path - CORRECT ANSWER - the longest continuous chain of activities through the network schedule that establishes the minimum overall project durations. Critical Path Characteristics - CORRECT ANSWER -must have a start and end date -path is continuous through to the end of the schedule -Convergence: activities have more than one predecessor -Divergence: activities have more than one successor Early start / Early finish - CORRECT ANSWER - -Longest path through schedule

Show more Read less
Institution
Cosc
Course
Cosc









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Cosc
Course
Cosc

Document information

Uploaded on
April 27, 2025
Number of pages
11
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

Cosc 475 Final ACTUAL UPDATED Exam
Questions and CORRECT Answers
crtical path - CORRECT ANSWER - the longest continuous chain of activities through the
network schedule that establishes the minimum overall project durations.


Critical Path Characteristics - CORRECT ANSWER - -Longest path through schedule
-must have a start and end date
-path is continuous through to the end of the schedule
-Convergence: activities have more than one predecessor
-Divergence: activities have more than one successor


Early start / Early finish - CORRECT ANSWER - Early Start (ES): The earliest an activity
can be started after all predecessors to the activity are completed.
Early Finish (EF): The earliest an activity can be finished given that activity's early start and
duration.


Late Start/late finish - CORRECT ANSWER - Late Start (LS): The latest an activity can
be started after all predecessors to the activity are completed.
Late Finish (LF): The latest that an activity can be finished and still complete the project within
the minimum overall duration determined by the forward pass.


Forward pass - CORRECT ANSWER - the process of navigating through a network from
start to end and calculating the early start and early finish dates for each activity and the finish
date for the entire project.
Goal: calculate the early start and finish dates
Result: what is the total project duration?


Backwards Pass - CORRECT ANSWER - the process of navigating through a network
from end to start and calculating the late start and finish dates. these dates determine the critical
activities, critical path, and the amount of float each activity has.

, goal: determine the LS & LF dates for each activity
result: what is the critical path of a project?


Slack/Float - CORRECT ANSWER - A number that indicates the amount of time a task
can be delayed without impacting subsequent tasks or the project's overall completion.
Task Slack = Late Start - Early Start
Task Slack = Late Finish - Early Finish


Most Owner contracts will dictate the duration of float that is required within the schedule.


Preconstruction activities - CORRECT ANSWER - -linear process of getting an acceptable
price
-Design activities
-Review of task list
-Procurement Activities
-Common Challenges (permits, cranes, community impact, etc)
-long lead items


Site logistics plan - CORRECT ANSWER - the sequencing and movement of materials,
people, and resources on and around construction sites


Uses of site logistic plan - CORRECT ANSWER - -safety
-transportation efficiency
-worker efficiency
-material handling
-security onsite
-inventory control
-housekeeping
-communication/coordination

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
MGRADES Stanford University
View profile
Follow You need to be logged in order to follow users or courses
Sold
1123
Member since
2 year
Number of followers
104
Documents
68962
Last sold
5 hours ago
MGRADES (Stanford Top Brains)

Welcome to MGRADES Exams, practices and Study materials Just think of me as the plug you will refer to your friends Me and my team will always make sure you get the best value from the exams markets. I offer the best study and exam materials for a wide range of courses and units. Make your study sessions more efficient and effective. Dive in and discover all you need to excel in your academic journey!

3.8

178 reviews

5
76
4
31
3
47
2
9
1
15

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions