COSC 475 Exam 2 UPDATED Exam Questions and CORRECT Answers If you are running a company and you have a limited number of labor resources but multiple different projects, would distance between the two projects impact your resource leveling options between the two projects? - CORRECT ANSWER - Yes You are a southern California contractor. You have been awarded two projects: one in downtown Los Angeles and one near the Mojave reservation. Each project needs a bulldozer and a crew of 4 at essentially the same time, each with a duration of about 3 weeks. The bulldozer helps accomplish essentially the first 3 weeks of work onsite. Would you share resources between these two projects when both projects have a fixed hard end date? - CORRECT ANSWER - No

Show more Read less
Institution
Cosc
Course
Cosc









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Cosc
Course
Cosc

Document information

Uploaded on
April 27, 2025
Number of pages
6
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

COSC 475 Exam 2 UPDATED Exam
Questions and CORRECT Answers
If you are running a company and you have a limited number of labor resources but multiple
different projects, would distance between the two projects impact your resource leveling options
between the two projects? - CORRECT ANSWER - Yes


You are a southern California contractor. You have been awarded two projects: one in downtown
Los Angeles and one near the Mojave reservation. Each project needs a bulldozer and a crew of 4
at essentially the same time, each with a duration of about 3 weeks. The bulldozer helps
accomplish essentially the first 3 weeks of work onsite. Would you share resources between
these two projects when both projects have a fixed hard end date? - CORRECT
ANSWER - No


If you build the same project 10 times in a row, same building but different locations, do you
always choose the same material management strategy? - CORRECT ANSWER - No


The leveling of resources looks at the overall fluctuations in day to day resource usage
throughout a project, labor and equipment, and attempts to do what to those fluctuations? -
CORRECT ANSWER - Minimize


When pertaining to labor, hourly workers are hired to perform which of the following? -
CORRECT ANSWER - All of the above


Are resource driven schedules and manpower loaded schedules the same thing? Meaning, are the
schedules both driven by the activities in the same way/manner? - CORRECT ANSWER -
No


Which of the following is not a method used to reduce fluctuations the resource profile when
resource leveling? - CORRECT ANSWER - Fast tracking activities

, The main idea of resource leveling is to increase the efficiency of the project and minimize the
overall costs. Leveling which of the following really does not assist in these cost reduction and
efficiency improvement efforts. - CORRECT ANSWER - Materials


Utilizing extreme theories like the inventory buffer theory, is it economical to have all materials
on-site before starting a project to achieve the lowest cost option project (Cost driven, not
schedule driven)? One clue, when referencing just all material being on-site before construction
starts, is that I would refer to this as "The Dream Project" - CORRECT ANSWER -
Uneconomical


If you are GC and have multiple large subcontractors that have labor resources in many states
and multiple crafts, should you bother to resource load your master schedule? - CORRECT
ANSWER - Yes


The assignment of resources required to complete a given activity, or work item, in the required
amount and timing is known as what? - CORRECT ANSWER - Resource allocation


When dealing with work space and the ever changing nature of the work during the life cycle of
a project, which of the following is not considered a work space consideration for planning and
resource leveling? - CORRECT ANSWER - All of the above should be considered


You are a southern California contractor. You have been awarded two projects: one in downtown
Los Angeles and one near the Mojave reservation. Each project needs a safety manager at
essentially the same time, each for a duration of about 6 weeks. Would you share resources
between these two projects when both projects have a flexible end date? The client on each
project has stated that a safety manager will be on-site each day for at least half the days work
duration when crews are on-site. - CORRECT ANSWER - No


We often talk about the backward pass when looking at schedule logic; is there a similar step that
can be done with resource leveling? - CORRECT ANSWER - Yes


When working with our schedules, we are dealing specifically with crews in our resource
calendar. When utilizing a manpower loaded schedule, as we are for HW6 and the semester

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
MGRADES Stanford University
View profile
Follow You need to be logged in order to follow users or courses
Sold
1123
Member since
2 year
Number of followers
104
Documents
68962
Last sold
5 hours ago
MGRADES (Stanford Top Brains)

Welcome to MGRADES Exams, practices and Study materials Just think of me as the plug you will refer to your friends Me and my team will always make sure you get the best value from the exams markets. I offer the best study and exam materials for a wide range of courses and units. Make your study sessions more efficient and effective. Dive in and discover all you need to excel in your academic journey!

3.8

178 reviews

5
76
4
31
3
47
2
9
1
15

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions