questions with verified answers
Only one quote was received in response to your competitive solicitation for
Government-unique tool kits that utilized the lowest price technically acceptable
source selection process. The quote, from Tool Warehouse, was determined to be
technically acceptable and was for a price of $124,500.
Which one of the following statements about the award decision is correct?
Ans✓✓✓ Not - The requirement must be reconsolidated in order to obtain
competition.
Six quotes were received in response to your solicitation for new office
equipment that utilized the lowest price technically acceptable source selection
process. The quotes submitted by vendors A, B, and D were determined to be
technically acceptable.
Vendor A quoted a price of $146,500;Vendor B quoted a price of $128,250; and
Vendor D quoted a price of $132,800.
Which one of the following statements about the award decision is correct?
Ans✓✓✓ Vendor B is the apparent awardee and price reasonableness would be
based on competition
Take 13 Ans✓✓✓ take 13
Three quotes were received in response to your solicitation for training services.
Evaluation was based on a tradeoff between price and past performance. The
assigned past performance ratings and quoted prices were as follows:
Vendor A - Unacceptable, $216,150;
,Vendor B - Acceptable, $248,500; and
Vendor C - Outstanding, $237,200.
Which one of the following statements about the award decision is correct?
Ans✓✓✓ Not - Vendor B is the apparent awardee and price reasonableness
could be based on any reasonable basis
Not - Vendor A is the apparent awardee and price reasonableness would be based
on competition
Vendor c
Which one of the following is correct regarding documenting the award of a buy
using SAP? Ans✓✓✓ Not - Award documentation must be extensive and detailed
Not - Records of oral price quotations are not required
Not - Records of oral price quotations must be established to clearly reflect the
appropriateness of the award decision.
Not - Comparison of competitive quotes or offers is the least preferred method
for determining price reasonableness.
Which one of the following is NOT a mandatory Government source for satisfying
a supply requirement? Ans✓✓✓ Not - Excess from other agencies
, Not - Wholesale supply sources
Commercial sources
Which one of the following is NOT correct regarding documenting the award of a
buy using SAP? Ans✓✓✓ 19. Maybe not - Records of oral price quotations must
be established to clearly reflect the appropriateness of the award decision.
Not - Price reasonableness should be based on competitive quotes or offers
whenever possible.
Not - A statement of price reasonableness is not required when only one quote or
offer is received.
Which one of the following is NOT one of the first steps taken when quotations
are received in response to a solicitation using SAP? Ans✓✓✓ Not - Reviewing
the quotations for responsibility
Not - Reviewing electronic and digital submission to ensure they are readable
Not - Ranking the quotations by technical acceptability
Ensuring quotations are marked with the date and time they were received
7. Documenting the quotations with the date and time they were received