1|Page
Bailey Bridge Exam 2025 Actual exam (Testing Real
Exam Questions)and verified Answers ( 100%
accurate) GET IT RIGHT!!
Given a 210-foot TT bridge. What is the position of launching-nose links? -
(answer)30x40ft
How many personnel does the routine repair detail consists of? - (answer)6
How many personnel does the maintenance party usually consist of for important
bridges subject to enemy action? - (answer)entire assembly crew
What is the required safety setback on an unprepared abutment if the bank
height is 6 feet? - (answer)(1.5) 6ft = 9ft
Given a 140-foot TS bridge with grillage type 1 on both the near shore (NS) and far
shore (FS). The far-bank seat is level with the near-bank seat. What is the position
of the launching-nose links? - (answer)20x40ft
How is the initial bridge length determined? - (answer)adding the width of the
gap, the safety setbacks, and the
roller clearances.
What is the purpose of construction rollers? - (answer)Aid in inserting the
launching-nose links and provide clearance between the links and the ground
Bailey Bridge Exam 2025 Actual exam (Testing Real
Exam Questions)and verified Answers ( 100%
accurate) GET IT RIGHT!!
Given a 210-foot TT bridge. What is the position of launching-nose links? -
(answer)30x40ft
How many personnel does the routine repair detail consists of? - (answer)6
How many personnel does the maintenance party usually consist of for important
bridges subject to enemy action? - (answer)entire assembly crew
What is the required safety setback on an unprepared abutment if the bank
height is 6 feet? - (answer)(1.5) 6ft = 9ft
Given a 140-foot TS bridge with grillage type 1 on both the near shore (NS) and far
shore (FS). The far-bank seat is level with the near-bank seat. What is the position
of the launching-nose links? - (answer)20x40ft
How is the initial bridge length determined? - (answer)adding the width of the
gap, the safety setbacks, and the
roller clearances.
What is the purpose of construction rollers? - (answer)Aid in inserting the
launching-nose links and provide clearance between the links and the ground