When does acquisition planning begin?
After the acquisition plan has been written.
Shortly after the customer need is identified.
After market research is conducted.
As soon as the agency need is identified.
Feedback:Correct, see FAR 7.104(a). See U03, Lesson 01.
Correct 2/2 Points
In which part of the Federal Acquisition Regulation (FAR), can information concerning
acquisition planning and written acquisition plans be found?
FAR part 9
FAR part 7
Feedback:Correct, see FAR part 7. See U03, Lesson 01.
FAR part 6
FAR part 4
Correct 2/2 Points
For DoD, who has overall responsibility for the acquisition planning effort?
The subject matter experts working on the acquisition.
Program manager or other official responsible for the acquisition.
Feedback:Correct, see DFARS 207.103(g). See U03, Lesson 01.
Program manager and the Contract Specialist working on the acquisition.
Contracting officer and other contracting professionals working on the acquisition.