100% Solved
Quality Control (QC) engineering unit's system in place during execution to manage,
control, and document the unit's activities in compliance with the project plans and specifications
requirements
Unit QC Plan unit QC manager and assigned QC specialists perform and direct activities
to execute unit level QC program
Project QC Plan - project managers and project supervisors perform and direct activities
to develop individual project QC plan
Quality Assurance (QA) planned and systematic pattern of all actions necessary to
provide confidence that adequate technical requirements are established, that products and
services conform to those requirements, and satisfactory performance is achieved
,Types of construction Permanent, Semi-permanent, Temporary
Permanent Life expectancy greater than 25 years
Low maintenance cost
Only executed by USACE
Semi-permanent Life expectancy between 5-25 years
Only executed by USACE
Troop construction may be used
Temporary Life expectancy less than 5 years
Can be easily removed
Typical troop construction
, Laws Misappropriation Act - Don't use the wrong color of money or money allocated to
other projects
Anti Deficiency Act - Don't spend money you don't have
Don't split projects to get below the funding thresholds
Current working estimates Latest and most accurate cost estimate
Continuously updated throughout the project to reflect real and projected costs
Includes all cost associated with project
Used to analyze costs and control design decisions to keep the project within the approved funds
and scope
Lead: overlap between tasks that have a dependency. For example, if a task can start
when its predecessor is half-finished, you can specify a finish-to-start dependency with a lead
time of 50% its successor (negative value)