Who are the four teams that make up a project team - CORRECT
ANSWER The Owner Team
The Design Team
The Contractor Team
The Supplier Team
Who composes the Owner Team? - CORRECT ANSWER Public and
private owners, owner advisors, owner consultants, occupants, utility,
service providers, and authorities having jurisdiction
Who composes the Design Team? - CORRECT ANSWER Architects,
engineering consultants and specialty consultants
Who composes the Supplier Team? - CORRECT ANSWER
Manufacturers, distributors, suppliers and fabricators
What are the responsibilities of the owner team? - CORRECT ANSWER
initiated the project
assumes risk
provides funding, control, and management of the design and
construction process
approves of design and construction activates
acts as the principle stakeholder
What are the responsibilities of the design team? - CORRECT ANSWER
Addresses planning issues, including those involving AHJ
Assists in determining design program and requirements
Reflects owner's visions and meets design program and requirements
Identifies applicable codes and regulations
Researches, evaluates, and selects products
Produces construction documents
Administers construction contract
,Provides QA/QC
What are the responsibilities of the Construction team? - CORRECT
ANSWER estimates costs
schedules time
manages construction
What are the responsibilities of the Supplier team? - CORRECT
ANSWER Produces materials, product, equipment for project
Furnishes products or services
Assembles materials, products and equipment offsite
What are the four C's of effective communication - CORRECT ANSWER
Clear, concise, correct, complete
What are the Facility Life Cycle Stages - CORRECT ANSWER Project
Conception
Design
Construction Documents
Procurement
Construction
Facility Management
What are the 6 taxonomical and compositional formats? - CORRECT
ANSWER OmniClass
UnitFormat
Master Format
SectionFormat
PageFormat
PPDFormat
Define OmniClass - CORRECT ANSWER Classifies information
applicable to the entire built environment
Provides a classification structure for electronic databases
Includes 15 classification tables
Uses Unit Format and Mater Format
,Define UniFormat - CORRECT ANSWER Organizes construction
information based on fictional elements or systems and assemblies
Promotes standardization
Facilitates retrieval of information
Classifies information into 8 elements
Define Masterformat - CORRECT ANSWER Organizes construction,
operation and maintenance information based in work results
Arranges related work results into Divisions
Promotes standardization and improves construction communication
Comprised of two groups ( procurement and Contracting
Requirements, Specifications)
Define SectionFormat - CORRECT ANSWER Organizes content within
a signal specification section
Utilizes a MasterFormat number and title for each specification
section
Establishes an organizational structure consisting of three (3) part
(part 1 General, Part 2 Products, Part 3 Execution)
Define PageFormat - CORRECT ANSWER Standardizes presentation
of specification information on the printed page
Simplifies preparation, review and publication tasks
Lays out text of a Master Format specification section in a
standardized format
Define PPDFormat - CORRECT ANSWER Develops preliminary project
descriptions (PPDs)
Standardizes preliminary project information using description of basic
systems and assemblies
Uses UniFormat as the structure for a PPD
National BIM Standard- United States (NBIMS-US) - CORRECT
ANSWER is a digital representation of physical and functional
characteristics of a facility
What are the 3 parts of a contract? - CORRECT ANSWER offer,
acceptance, consideration
, Spearin Doctrine - CORRECT ANSWER A US supreme Court decision
in 1918, siding with the contractor who lost a contract despite building
in conformance with drawings
outcome holds that a contractor is entitled to rely on the construction
documents provided by the owners to be sufficient for intended
purpose
Contractor must show that defects in plans and/or specification were
the cause for any unacceptable work or adversely affected the cost or
time to complete work.
What are the 6 fundamental design approaches - CORRECT ANSWER
site optimization
energy performance and conservation
water use and conservation
materials and resources
environmental quality
Historic preservation and rehabilitation
Construction Documents Contain - CORRECT ANSWER Procurement
requirements
Contract Forms
Project Forms
Conditions of the Contract
Specification
Drawings
Addenda (pre- Contract Revisions)
Contract Modification
Procurement Documents Contrail - CORRECT ANSWER Procurement
requirements
Contract Forms
Project Forms
Conditions of the Contract
Specification
Drawings
Addenda (pre- Contract Revisions)