FCCM - Answer✔Florida Certified Contract Manager, 287. 601a
How many stages in Public Procurement? - Answer✔7
1st Stage - Answer✔Identification Stage:
* Need id
* budget id
* purchasing strategy
Objective for (Need ID Stage) - Answer✔Identify the categories of purchases available to use
when contracting for commodities or contractual services.
What would be an procurement purchase that cannot be delayed? - Answer✔Emergency
Purchases (Non-Competitive)
1|Page
, ©THESTAR 2025 ALL RIGHTS RESERVED 11:41 AM A+
Exceptional Purchases (Non-Competitive) - Answer✔* Respect
* Pride
* State Term Contract (STC)
* Alternative Contract Source (ACS)
*Single Source
* Exempt Commodities and Contractual Services,
Rule 60A-1.002(4)
Competitive Solicitation - Answer✔The total cost of the commodities or contractual services
exceed services exceeds 35,000 (Category 2)
What is stage 2 process called? - Answer✔Pre-Solicitation Process:
Develop background information needed for a successful competitive solicitation and which
method is appropriate.
Stage 2: Payment Methods - Answer✔* Cost Reimbursement
* Fixed Price
* Fixed Rate