NCCER Module 44106 - Construction Planning
Questions And Answers 100% Verified
The uterm ucommonly uused uto udefine uthe uprocess uof uacquiring umaterials uand uother
ucommodities ufor ua uproject uis
a) upurchase uorder
b) upurchasing
c) uacquisition
d) ushopping u- uCorrect uAnswer-b) upurchasing
In upre-construction uplanning, uthe uphase uthat uoccurs ufirst uis
a) uconcept udesign
b) uwork umethods uand uresources
c) upersonnel urequirements uidentification
d) ubid udevelopment u- uCorrect uAnswer-d) ubid udevelopment
A ugeneral urule ufor ubreaking ua uproject udown uinto ujobs uand uactivities uis uthat ueach uactivity
ushould ube
a) uidentifiable uand udefinable
b) usimple uand uunderstandable uc) ugeneral uand ureasonable
d) uprecise uand ulogical u- uCorrect uAnswer-a) uidentifiable uand udefinable
If ua upurchase uorder uto ua uvendor uindicates ushipment uis u"FOB uFactory," uit umeans
a) uthe ubuyer uis uexpected uto upick uup uthe umaterial uat uthe ufactory
b) uthe utitle uand uresponsibility ufor uthe umerchandise utransfers uas usoon uas uit uis uloaded uat
uthe ufactory
c) uthe utitle uand uresponsibility ufor uthe umerchandise ubelongs uto uthe useller uuntil uit uhas
ubeen udelivered
d) uthe uvendor uexpects uthe uinvoice uto ube upaid ubefore uthe umaterial ucan ube uloaded uat uthe
ufactory u- uCorrect uAnswer-b) uthe utitle uand uresponsibility ufor uthe umerchandise utransfers
uas usoon uas uit uis uloaded uat uthe ufactory
6. uTo uensure usmooth uworkflow, uthe uproject umanager ushould
(a) uspend utime uwith ufield usupervisors
b) umeet uwith uindividual ucrews
c) umeet uwith uthe uproject uengineer
d) ufocus uon usubcontractors' uperformance u- uCorrect uAnswer-a) uspend utime uwith ufield
usupervisors
A ugood upractice uto uensure utool uinventories uare uaccurate uis uto uuse
a) ucolor ucoding
b) uself-adhesive ulabels uwith uID unumbering
c) uengraving
d) ubar ucoding u- uCorrect uAnswer-d) ubar ucoding
Questions And Answers 100% Verified
The uterm ucommonly uused uto udefine uthe uprocess uof uacquiring umaterials uand uother
ucommodities ufor ua uproject uis
a) upurchase uorder
b) upurchasing
c) uacquisition
d) ushopping u- uCorrect uAnswer-b) upurchasing
In upre-construction uplanning, uthe uphase uthat uoccurs ufirst uis
a) uconcept udesign
b) uwork umethods uand uresources
c) upersonnel urequirements uidentification
d) ubid udevelopment u- uCorrect uAnswer-d) ubid udevelopment
A ugeneral urule ufor ubreaking ua uproject udown uinto ujobs uand uactivities uis uthat ueach uactivity
ushould ube
a) uidentifiable uand udefinable
b) usimple uand uunderstandable uc) ugeneral uand ureasonable
d) uprecise uand ulogical u- uCorrect uAnswer-a) uidentifiable uand udefinable
If ua upurchase uorder uto ua uvendor uindicates ushipment uis u"FOB uFactory," uit umeans
a) uthe ubuyer uis uexpected uto upick uup uthe umaterial uat uthe ufactory
b) uthe utitle uand uresponsibility ufor uthe umerchandise utransfers uas usoon uas uit uis uloaded uat
uthe ufactory
c) uthe utitle uand uresponsibility ufor uthe umerchandise ubelongs uto uthe useller uuntil uit uhas
ubeen udelivered
d) uthe uvendor uexpects uthe uinvoice uto ube upaid ubefore uthe umaterial ucan ube uloaded uat uthe
ufactory u- uCorrect uAnswer-b) uthe utitle uand uresponsibility ufor uthe umerchandise utransfers
uas usoon uas uit uis uloaded uat uthe ufactory
6. uTo uensure usmooth uworkflow, uthe uproject umanager ushould
(a) uspend utime uwith ufield usupervisors
b) umeet uwith uindividual ucrews
c) umeet uwith uthe uproject uengineer
d) ufocus uon usubcontractors' uperformance u- uCorrect uAnswer-a) uspend utime uwith ufield
usupervisors
A ugood upractice uto uensure utool uinventories uare uaccurate uis uto uuse
a) ucolor ucoding
b) uself-adhesive ulabels uwith uID unumbering
c) uengraving
d) ubar ucoding u- uCorrect uAnswer-d) ubar ucoding