CQM -C EXAM STUDY QUESTIONS AND
ANSWERS
The _____________________ consists of daily checks of the work to assure
continuing compliance with contract requirements.
Follow-up phase
The Quality Assurance Plan:
Is a government management tool establishing staffing, training, pre-award
activities, and surveillance activities.
Testing is extremely important in construction quality management and is
performed by:
Both the contractor and the government
If the contractor does not provide an adequate superintendent, the contract
allows the contracting officer to:
Require the contractor to assume personal supervision of the work.
The Quality Control Plan:
Is the foundation upon which quality work is based and outlines planned
quality control procedures.
Tests that are unannounced, randomly performed, and repeat quality
control tests are:
Quality Assurance tests
If initial review of the quality control plan shows it to be unacceptable:
The contractor makes changes before acceptance.
The contractor quality control organization:
, May vary in size depending on the work being performed at a point in time.
The Quality Control Plan contains:
Identification of individual quality quality control personnel, including name,
qualifications, assigned duties, responsibilities and authorities.
The preconstruction conference and the coordination and mutual
understanding meeting (Navy) are:
Conducted prior to the commencement of any physical construction work.
A cumulative list of job deficiencies/rework items can be found in:
A deficiency tracking system/reworks items list.
What is a purpose of the coordination and mutual understanding and
meeting (Navy)?
To review the QC Plan with the contractor.
Which of the following is included in all three phases of the Three Phases of
Control.
Safety.
Submittals are:
Necessary to demonstrate that the proposed materials, etc. are in compliance
with the contract.
All submittals for government approval must be provided by the
_________________ in time to allow for the review, approval, procurement,
delivery, and performance of preparatory phase for an item before it is
needed for construction.
Contractor to the Government
The means for enforcing contract compliance are provided in the:
ANSWERS
The _____________________ consists of daily checks of the work to assure
continuing compliance with contract requirements.
Follow-up phase
The Quality Assurance Plan:
Is a government management tool establishing staffing, training, pre-award
activities, and surveillance activities.
Testing is extremely important in construction quality management and is
performed by:
Both the contractor and the government
If the contractor does not provide an adequate superintendent, the contract
allows the contracting officer to:
Require the contractor to assume personal supervision of the work.
The Quality Control Plan:
Is the foundation upon which quality work is based and outlines planned
quality control procedures.
Tests that are unannounced, randomly performed, and repeat quality
control tests are:
Quality Assurance tests
If initial review of the quality control plan shows it to be unacceptable:
The contractor makes changes before acceptance.
The contractor quality control organization:
, May vary in size depending on the work being performed at a point in time.
The Quality Control Plan contains:
Identification of individual quality quality control personnel, including name,
qualifications, assigned duties, responsibilities and authorities.
The preconstruction conference and the coordination and mutual
understanding meeting (Navy) are:
Conducted prior to the commencement of any physical construction work.
A cumulative list of job deficiencies/rework items can be found in:
A deficiency tracking system/reworks items list.
What is a purpose of the coordination and mutual understanding and
meeting (Navy)?
To review the QC Plan with the contractor.
Which of the following is included in all three phases of the Three Phases of
Control.
Safety.
Submittals are:
Necessary to demonstrate that the proposed materials, etc. are in compliance
with the contract.
All submittals for government approval must be provided by the
_________________ in time to allow for the review, approval, procurement,
delivery, and performance of preparatory phase for an item before it is
needed for construction.
Contractor to the Government
The means for enforcing contract compliance are provided in the: