Select the best description of the Planning Process Group - ANSWERThe process
performed to define a new project or a new phase of an existing project by obtaining
authorization to start the project or phase
You are managing a project in which you intend to respond to high levels of change
and ongoing stakeholder involvement the most suitable project lifecycle for your
project is the: - ANSWERAdaptive life cycle
What is a formal proposal to modify a document, deliverable, or baseline? -
ANSWERChange request
Which of the following is an input to the plan schedule management process? -
ANSWERScope management plan
All of the following are true about the statement of work (SOW) for a procurement
EXCEPT: - ANSWERIt can be ambiguous or incomplete to allow for future
negotiations
Which of the following is an input to the plan communications management process?
- ANSWERProject charter
What does the develop project charter process entail? - ANSWERDeveloping a
document that formally authorizes the existence of a project and provides the project
manager with the authority to apply organizational resources to project activities
Which of the following best defines an accept strategy, within the Plan Risk
Response Process? - ANSWERAcknowledge the opportunity but take no proactive
action
Which of the following are considerations for tailoring processes for Project
Stakeholder Management? - ANSWERStakeholder diversity and communication
technology
Which of the following is the process of monitoring Project stakeholder relationships
and tailoring strategies for engaging stakeholders through modification of
engagement strategies and plans? - ANSWERMonitor Stakeholder Engagement
What input to the control cost process contains data on project status such as which
costs have been authorized incurred, invoiced, and paid? - ANSWERWork
performance data
Which of the following are inputs to close project or phase? - ANSWERProject
Charter, Accepted Deliverables, and Organizational Process Assets (OPAs)