Ram is a new project m anager leading the development of a new inventory management system. He just completed project management training and plans to follow a step-by-step planning process. Which sequence represents the correct project planning process? - ANSWERScope, Schedule, Cost The project team is reviewing the project charter and is creating a work breakdown structure (WBS). They subdivided the project scope into smaller and more manageable parts. Which process are they performing? - ANSWERDecomposition - is defined as dividing and subdividing the project scope into smaller and more manageable parts. A project manager appr eciates the value of lessons learned. The organization has set up a SharePoint site where all project managers file lessons learned reports after completing each project. Which method is used to document the lessons learned? - ANSWERLessons Learned Register All project lessons learned reports are filed in an Enterprise Lessons Learned register that all stakeholders have access to. The team is preparing to participate in a retrospective. Who facilitates a retrospective, and when is it required? - ANSWERScrum Masters facilitate retrospectives at the end of a Scrum or Agile project. A A work breakdown structure is organized as follows: Level 1 - 1 activity Level 2- 4 activities Level3-18activities The project team is preparing to create a project network diagram. How many activities should be represented in the network diagram? - ANSWER18 Only Ram is a new project m anager leading the development of a new inventory management system. He just completed project management training and plans to follow a step-by-step planning process. Which sequence represents the correct project planning process? - ANSWERScope, Schedule, Cost The project team is reviewing the project charter and is creating a work breakdown structure (WBS). They subdivided the project scope into smaller and more manageable parts. Which process are they performing? - ANSWERDecomposition - is defined as dividing and subdividing the project scope into smaller and more manageable parts. A project manager appr eciates the value of lessons learned. The organization has set up a SharePoint site where all project managers file lessons learned reports after completing each project. Which method is used to document the lessons learned? - ANSWERLessons Learned Register All project lessons learned reports are filed in an Enterprise Lessons Learned register that all stakeholders have access to. The team is preparing to participate in a retrospective. Who facilitates a retrospective, and when is it required? - ANSWERScrum Masters facilitate retrospectives at the end of a Scrum or Agile project. A A work breakdown structure is organized as follows: Level 1 - 1 activity Level 2- 4 activities Level3-18activities The project team is preparing to create a project network diagram. How many activities should be represented in the network diagram? - ANSWER18 Only

Show more Read less
Institution
CAPM
Course
CAPM








Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
CAPM
Course
CAPM

Document information

Uploaded on
February 28, 2025
Number of pages
4
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

  • capm practice exam

Content preview

CAPM Practice Exam: Domain 1 Project
Management Fundamentals and Core
Concepts QUESTIONS &ANSWERS
100% CORRECT
Ram is a new project m
anager leading the development of a new inventory management system. He just
completed project management training and plans to follow a step-by-step planning
process. Which sequence represents the correct project planning process? -
ANSWERScope, Schedule, Cost

The project team is reviewing the project charter and is creating a work breakdown
structure (WBS). They subdivided the project scope into smaller and more
manageable parts. Which process are they performing? - ANSWERDecomposition -
is defined as dividing and subdividing the project scope into smaller and more
manageable parts.
A project manager appr
eciates the value of lessons learned. The organization has
set up a SharePoint site where all project managers file lessons learned reports after
completing each project. Which method is used to document the lessons learned? -
ANSWERLessons Learned Register
All project lessons learned reports are filed in an Enterprise Lessons Learned
register that all stakeholders have access to.

The team is preparing to participate in a retrospective. Who facilitates a
retrospective, and when is it required? - ANSWERScrum Masters facilitate
retrospectives at the end of a Scrum or Agile project.

A
A work breakdown structure is organized as follows:
Level 1 - 1 activity
Level 2- 4 activities
Level3-18activities
The project team is preparing to create a project network diagram. How many
activities should be represented in the network diagram? - ANSWER18

Only Level 3 activities are represented in a project network diagram.

The project has entered the executing process group. The team performs periodic
audits to ensure the project is executed using prescribed processes and meeting the
mandatory standards. The primary objective is to avoid problems. Which process is
being performed? - ANSWERQuality assurance - uses audits to ensure the project is
executed using the prescribed processes and meeting the mandatory standards.

Risk metalanguage is a common method to document a risk. What is the correct risk
metalanguage sequence? - ANSWERCause, Event, Impact

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
nursingismylife West Virginia University
View profile
Follow You need to be logged in order to follow users or courses
Sold
248
Member since
2 year
Number of followers
174
Documents
9127
Last sold
1 week ago

3.6

38 reviews

5
14
4
12
3
3
2
1
1
8

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions