Ram is a new project m
anager leading the development of a new inventory management system. He just
completed project management training and plans to follow a step-by-step planning
process. Which sequence represents the correct project planning process? -
ANSWERScope, Schedule, Cost
The project team is reviewing the project charter and is creating a work breakdown
structure (WBS). They subdivided the project scope into smaller and more
manageable parts. Which process are they performing? - ANSWERDecomposition -
is defined as dividing and subdividing the project scope into smaller and more
manageable parts.
A project manager appr
eciates the value of lessons learned. The organization has
set up a SharePoint site where all project managers file lessons learned reports after
completing each project. Which method is used to document the lessons learned? -
ANSWERLessons Learned Register
All project lessons learned reports are filed in an Enterprise Lessons Learned
register that all stakeholders have access to.
The team is preparing to participate in a retrospective. Who facilitates a
retrospective, and when is it required? - ANSWERScrum Masters facilitate
retrospectives at the end of a Scrum or Agile project.
A
A work breakdown structure is organized as follows:
Level 1 - 1 activity
Level 2- 4 activities
Level3-18activities
The project team is preparing to create a project network diagram. How many
activities should be represented in the network diagram? - ANSWER18
Only Level 3 activities are represented in a project network diagram.
The project has entered the executing process group. The team performs periodic
audits to ensure the project is executed using prescribed processes and meeting the
mandatory standards. The primary objective is to avoid problems. Which process is
being performed? - ANSWERQuality assurance - uses audits to ensure the project is
executed using the prescribed processes and meeting the mandatory standards.
Risk metalanguage is a common method to document a risk. What is the correct risk
metalanguage sequence? - ANSWERCause, Event, Impact