EXAM QUESTIONS AND ANSWERS 100%
GRADED AT A+
1. The purpose of Construction Quality Management is to: -
ANSWER Achieve the quality established by properly developed
requirements through the combined responsibility, but seperate
efforts of contractpr smd government personnel.
2. Which of the following is included in all three phases of the Three
Phases of Control. - ANSWER Safety.
3. Submittals are: - ANSWER Necessary to demonstrate that the
proposed materials, etc. are in compliance with the contract.
4. All submittals for government approval must be provided by the
_________________ in time to allow for the review, approval,
procurement, delivery, and performance of preparatory phase for
an item before it is needed for construction. - ANSWER Contractor
to the Government
5. The means for enforcing contract compliance are provided in the: -
ANSWER Contract clauses of the contract.
, 6. ENG Form 4288-R, the submittal register: - ANSWER Identifies
those submittals requiring government approval
7. The primary purpose of the Three-Phase control system is to: -
ANSWER Require the contractor to plan and schedule his work.
8. The contractor is required to conduct a preparatory phase meeting
before he begins any definable feature of work except when: -
ANSWER There are no exceptions to the rule.
9. The ____________________ is the appropriate time to assure that
all materials and/or equipment have been tested, submitted, and
approved. - ANSWER Preparatory phase
10. Construction Quality Management is the performance of
tasks, which ensure that construction is performed. - ANSWER
According to plans and specifications, on time, within a defined
budget and a safe work environment.
11. Partnering relationships are based upon: - ANSWER
Building trust and dedication to common goals
12. It is the responsibility of Quality Assurance Personnel to: -
ANSWER Periodically verify that the contractors system of
control is working effectively.