F60 FIREGUARD TEST EXAM 2025 WITH GUARANTEED ACCURATE ANSWERS
For hot work operation with citywide permit, the owner of the premises
of the hot work operation areas must be notified in writing by the
citywide permit holder ______ the hot work is to be started. -
ACCURATE ANSWERS✔✔ at least 48 hours before
The pre-hot work check must be conducted by the responsible person
before hot work is authorized and __________ - ACCURATE
ANSWERS✔✔ least once per day.
The check reports must be kept at the work site during the work, made
available for inspection by a representative of the FDNY, and maintained
on the premises for a minimum of - ACCURATE ANSWERS✔✔ 48
hours after work is complete.
, A pre-hot work check must be conducted at least - ACCURATE
ANSWERS✔✔ once per day
Hot work operations involving cutting or welding shall be conducted at
least - ACCURATE ANSWERS✔✔ 35 feet from combustible materials
and combustible waste
All other hot work operations shall be conducted at least - ACCURATE
ANSWERS✔✔ 25 feet from combustible materials and combustible
waste
Sprinkler system protection ____________while hot work is performed.
- ACCURATE ANSWERS✔✔ must not be shut off or impaired
When should a Fire watch be maintained - ACCURATE ANSWERS✔✔
A fire watch must be maintained during any hot work operation.
What other duties should the Fire Watch have while on hot water
operations. - ACCURATE ANSWERS✔✔ The persons conducting a fire
watch shall not have other duties.
Where hose lines are required, they shall be connected, charged and
ready for operation - ACCURATE ANSWERS✔✔ At least one portable
fire extinguisher with a minimum 2-A:20-B:C