CON 1400V Day 4 - Managing Changes v3.1-Test
Questions and Answers |Latest Update
Scenario 1: You are the contracting officer for contract W0054219P0052 for the delivery of
five rail carts. Two weeks after the contract was awarded, the requiring activity informed you
that they need to add two additional characteristics to the salient characteristics in
Attachment 0001. [Note: You can
find a copy of this contract in the "Handouts & Infographs" section of the MS Teams
Classroom.] These additional characteristics will change the form, fit, and function of the rail
carts. The requiring activity is willing to change the delivery date to 30 days later than the
current schedule as part of the
Government's consideration for the contractor, Acme, accommodating this change. Is this
proposed change within the general scope of the current contract?
No, this proposed change does not pass either of the scope tests.
How could you execute the requiring activity's request for a change?
Negotiate a supplemental agreement after first addressing competition via a J&A
If this change will be accomplished through a modification to the current contract, will the
modification be executed as a unilateral or a bilateral modification?
Bilateral Modification signed by both the contracting officer and contractor
What would be the authority for the modification?
52.212-4(c)
What SF 30, Block 13 would you check?
Block C
Scenario 2: You are the contracting officer for contract W0054219P0052 for the delivery of
five rail carts. [Note: You can find a copy of this contract in the "Handouts & Infographs"
section of the MS Teams Classroom.] One month after award, you receive notice from the
Questions and Answers |Latest Update
Scenario 1: You are the contracting officer for contract W0054219P0052 for the delivery of
five rail carts. Two weeks after the contract was awarded, the requiring activity informed you
that they need to add two additional characteristics to the salient characteristics in
Attachment 0001. [Note: You can
find a copy of this contract in the "Handouts & Infographs" section of the MS Teams
Classroom.] These additional characteristics will change the form, fit, and function of the rail
carts. The requiring activity is willing to change the delivery date to 30 days later than the
current schedule as part of the
Government's consideration for the contractor, Acme, accommodating this change. Is this
proposed change within the general scope of the current contract?
No, this proposed change does not pass either of the scope tests.
How could you execute the requiring activity's request for a change?
Negotiate a supplemental agreement after first addressing competition via a J&A
If this change will be accomplished through a modification to the current contract, will the
modification be executed as a unilateral or a bilateral modification?
Bilateral Modification signed by both the contracting officer and contractor
What would be the authority for the modification?
52.212-4(c)
What SF 30, Block 13 would you check?
Block C
Scenario 2: You are the contracting officer for contract W0054219P0052 for the delivery of
five rail carts. [Note: You can find a copy of this contract in the "Handouts & Infographs"
section of the MS Teams Classroom.] One month after award, you receive notice from the