100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

Additional NERC Exam Study Questions Emergency Preparedness 2025/2026 With Completed & Verified Solutions.

Rating
-
Sold
-
Pages
7
Grade
A+
Uploaded on
14-02-2025
Written in
2024/2025

Additional NERC Exam Study Questions Emergency Preparedness 2025/2026 With Completed & Verified Solutions.

Institution
NERC
Course
NERC









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
NERC
Course
NERC

Document information

Uploaded on
February 14, 2025
Number of pages
7
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

Additional NERC Exam Study Questions
Emergency Preparedness

Q1: For the annual test of an entity's back-up functionality Operating Plan to be valid, it
must demonstrate which of the following?
A) Back-up functionality is maintained for at least 2 continuous hours
B) All shift personnel are comfortable at the backup site
C) Transition time is one hour or less
D) The backup site is secure - ANS A) Back-up functionality is maintained for at least 2
continuous hours
\Q2: A BA is experiencing low voltage in the northeast region. A 50 MVA generator in that
area is loaded at 50 MWs. What action could a System Operator take to increase the
voltage in that area?
A) Increase generation to overload capacity
B) Decrease reactive power until voltage increases
C) Do nothing; the AVR will take care of it
D) Decrease real power and increase reactive power - ANS D) Decrease real power and
increase reactive power
\Q3: Maintenance in the area has resulted in the ICCP communication line being cut to
the control room. Which of the following actions is most appropriate?
A) Implement the plan for Loss of Control Center Functionality
B) Manually update State Estimator with the most current information
C) Report the loss of ICCP to NERC
D) Switch AGC to Flat Frequency Control - ANS C) Report the loss of ICCP to NERC
\Q4: A portion of a Reliability Coordinator Area is experiencing low voltage. What
Operating Instructions should the RC issue?
A) Lower transfers across area and decrease generation
B) Increase transfers across area and decrease generation
C) Lower transfers across area and increase generation
D) Increase transfers across area and increase generation - ANS C) Lower transfers
across area and increase generation
\Q5: Interconnection frequency is at 59.85 Hz. The System Operator has not experienced
any disturbances. What does this indicate?
A) Interconnection voltage and load are not balanced
B) Interconnection system loads are higher than on-line generation
C) Collective system generation is higher than system load
D) A loss of load - ANS B) Interconnection system loads are higher than on-line
generation
\Q6: As a general rule of thumb, a 5% reduction in customer voltage will lead to what
level of reduction in load magnitude?
A) 1.0%

, B) 3.0%
C) 5.0%
D) 6.3% - ANS B) 3.0%
\Q7: You receive an alarm that indicates low gas pressure on a SF6 transmission breaker.
Indications show the pressure is continuing to drop. What action would you take?
A) Isolate the breaker and dispatch maintenance personnel to inspect
B) Operate the breaker to see if the alarm will clear
C) Reduce the power flow through the breaker
D) Wait to see if the breaker trips - ANS A) Isolate the breaker and dispatch maintenance
personnel to inspect
\Q8: Which of the following is used to help balance a system after it separates from the
Interconnection during a disturbance?
A) Automatic Under-Frequency Load Shed {UFlS)
B) Automatic Under-Voltage Load Shed {UVLS)
C) Generator under-frequency trips
D) Automatic Generation Control {AGC) - ANS A) Automatic Under-Frequency Load Shed
{UFlS)
\Q9: In the initial stages of a restoration condition, high transmission system voltage
problems are more likely than low transmission system voltage problems. Why?
A) Because of the excessive MVAR supply from too many on-line generators
B) Because of the deficiency in MVAR from too much customer load energization
C) Because of the deficiency in MWs from too much customer load energization
D) Because of the excessive MVAR supply from the energization of transmission lines -
ANS D) Because of the excessive MVAR supply from the energization of transmission
lines
\Q10: A system operator has exhausted all available resources and re-dispatch options.
System voltage continues to decline. What should the system operator do next?
A) Contact the Reliability Coordinator
B) Shed load in the low voltage area
C) Start a VAR import schedule
D) Check on the under-voltage settings - ANS B) Shed load in the low voltage area
\Q11: A geomagnetic disturbance is predicted to occur tomorrow. Which parts of the
system are most likely to experience problems?
A) HVDC transmission lines
B) Delta connected transformers
C) Wye connected transformers
D) Large generators - ANS C) Wye connected transformers
\Q12: A severe disturbance has caused a total system shutdown. ou are in the process of
initiating system restoration procedures. An open all breaker command is an option on
your EMS system. What would be the consequences of using this command?
A) Restoration would take longer
B) Critical substation battery would be depleted
C) Visual inspect ion is needed prior to breaker operation

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
LEWIS12 Howard Community College
View profile
Follow You need to be logged in order to follow users or courses
Sold
23
Member since
1 year
Number of followers
1
Documents
1013
Last sold
5 days ago

3.3

3 reviews

5
1
4
0
3
1
2
1
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions