and Answers| Latest Update
General liability requirements in order to receive certificate of registration 100,000$
combined single limit for body and property damage
300,000$ aggregate for each year
Must include PRODUCTS, and COMPLETED OPERATIONS.
Registered firm should send new application if there is a complete change in ownership __ days
before change? 14 days BEFORE ownership change. Send in NEW application
If your license or certificate of registration is removed/revoked/denied how long will you have to
wait to re-apply? One year from date of removal/revoked. Unless SFM has heating and
says otherwsise
NFPA 24 Standard for the Installation of Private Fire Service Mains and Their
Appurtenances
NFPA 22 Standard for Water Tanks for Private Fire Protection
NFPA 30 Flammable and Combustible Liquids Code
, "Install" Install is defined in this chapter as the
"Initial placement of equipment or extension, modification, alteration of equipment AFTER the
initial placement
RME-UNDERGROUND can plan, install, maintain, or service underground fire mains. True or
false? FALSE.
RME-underground licensee can do everything besides PLAN underground fire mains.
RME-Dwelling can ? A licensee who can plan, install, service, maintain fire sprinkler
systems in one-two family dwellings and manufactured homes.
RME-General can? A licensee who is designated by registered firm to assure that ANY
fire sprinkler system as planned, designed, installed, maintained or serviced meets standard
provided by law
RME-General inspector can? licensee who can ONLY perform inspection, testing and
maintenance service for fire sprinkler system.
Must display certificate of registration on which documents? On any bids, proposals,
offers, and install drawings
Must display certificate of registration where? In conspicuous place at place of business.