100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

Residential Electrical Inspector - E1 National Certification Exam

Rating
-
Sold
-
Pages
130
Grade
A+
Uploaded on
08-02-2025
Written in
2024/2025

Below is a detailed content outline for the exam: 1. General Requirements (10%) • Project Administration (1%) o Verify that required permits are issued and valid. o Ensure that approved plans and specifications are available and retained as required. • Public Information and Legal (1%) o Communicate the intent of the code using proper terminology. o Answer questions about general code compliance, procedures, and materials. o Identify the suitability of materials based on listing and labeling. o Maintain inspection reports, correction notices, stop work orders, and data for the issuance of the certificate of occupancy. • Electrical Theory (2%) o Apply basic electrical theory to determine loads and circuit ampacities for safe installation of electrical systems. • Clearances and Guarding (2%) o Determine required working clearances, location, access, and guarding requirements for electrical installations. • Connections and Splices (2%) o Verify that conductor connections, splices, and terminal identification meet code requirements. • Conductors (2%) o Inspect conductors to verify correct use, type, insulation, markings, and ampacity. 2. Services (17%) • Service Size and Rating (8%) o Inspect services to verify required conductor ampacity, clearances, location, materials, and equipment. • Service Grounding and Bonding (9%) o Verify size and type of conductors and electrodes, including location and installation. 3. Branch Circuit and Feeder Requirements (28%) • Feeders (5%) o Inspect feeders to verify conductor size, clearances, location, materials, and grounding conductors. • Branch Circuit and Feeder Calculations (6%) o Verify that the load to be placed on branch circuits and feeders meets code provisions for the conductor, devices, materials, and equipment installed. • Branch Circuit Ratings and Overcurrent Protection (7%) o Verify correct size, type, location, and installation of overcurrent devices. • Required Branch Circuits (5%) o Verify that all required branch circuits are provided. • Panelboards (5%) o Verify panelboard rating, circuit identification, overcurrent protection, and correct installation. 4. Wiring Methods and Power and Lighting Distribution (21%) • Installation Methods (4%) o Verify that installation of all conductors, cables, raceways, and fittings meets code requirements. o Verify that underground wiring meets code requirements. • Branch Circuit Required Outlets (4%) o Verify that receptacle and lighting outlets and switches are provided in all required locations. • Branch Circuits – GFCI (4%) o Verify that ground-fault circuit interrupter protection is provided in all required locations. • Boxes and Enclosures (3%) o Verify that boxes are of proper type and correctly sized and installed. • Equipment Grounding (3%) o Verify equipment bonding and grounding conductor sizes, connections, and installation. • Flexible Cords (2%) o Verify proper use and sizing of flexible cords. • Class 2 Circuits (1%) o Inspect low voltage control wiring, Class 2 circuits, and fire alarm circuits. 5. Devices, Lighting Fixtures, and Appliances (19%) • Switches and Receptacles (6%) o Verify that switches and receptacles are of the correct type and rating and are installed properly. • Light Fixtures (4%) o Verify that light fixtures and fixture wires are of correct type and rating and are properly installed. • Appliances (5%) o Inspect appliance wiring and equipment to verify correct type, use, installation, and disconnecting means. • Heating and Cooling Equipment (4%) o Inspect space heating and cooling equipment, including air conditioning and refrigeration wiring and equipment, to verify correct type, use, installation, and disconnecting means.

Show more Read less
Institution
Computers
Course
Computers











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Computers
Course
Computers

Document information

Uploaded on
February 8, 2025
Number of pages
130
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

Residential Electrical Inspector - E1 National Certification Exam

Total 500 plus [Questions & Answers with Full Explanations]

Question 1:
An inspector arrives at a new residential construction site. Which of the following is the best first
step regarding project administration?
a) Verify that required permits have been issued and are valid.
b) Immediately start the on-site inspection without paperwork.
c) Request the contractor’s verbal confirmation that all permits are in order.
d) Begin the inspection by checking the electrical panel only.

Answer: a) Verify that required permits have been issued and are valid.

Explanation: Before any on‐site work is done, the inspector must confirm that all required
permits are properly issued and current. This ensures that the project complies with local
jurisdiction requirements and that the approved plans are in place.



Question 2:
During an inspection, you notice that the approved plans are not readily available on site. What is
the proper course of action?
a) Note the absence in the inspection report and continue.
b) Require the contractor to produce a copy of the approved plans immediately.
c) Immediately issue a stop work order until the plans are produced.
d) Ignore it, assuming the plans will be available at the certificate issuance stage.

Answer: b) Require the contractor to produce a copy of the approved plans immediately.

Explanation: Inspectors must ensure that approved plans and specifications are available and
retained as required. Failure to have these documents on site can hinder a proper evaluation of
code compliance.



Question 3:
Which document is most important for establishing that an electrical installation complies with
the approved design?
a) The original construction contract
b) The set of approved electrical plans and specifications
c) The warranty documentation provided by the manufacturer
d) The electrician’s personal notes

Answer: b) The set of approved electrical plans and specifications

,Explanation: Approved plans and specifications serve as the benchmark for what is permitted;
they define the required methods and materials for the installation. This documentation must be
maintained and available for review during inspections.



Question 4:
If a permit appears to have expired, what is the inspector’s best course of action?
a) Immediately issue a violation citation.
b) Contact the permitting authority to verify the permit’s status before proceeding.
c) Ignore the expiration if the work appears compliant.
d) Allow work to continue as long as the contractor assures compliance.

Answer: b) Contact the permitting authority to verify the permit’s status before proceeding.

Explanation: The inspector must verify the permit’s status with the issuing authority. An
expired permit can indicate that the project is not officially approved, and further work may be
unauthorized.



Question 5:
When reviewing a project file, you should verify that:
a) Only the electrical plans are on file.
b) A complete set of approved plans and specifications is available for every discipline involved.
c) The project manager’s resume is included.
d) The contractor’s insurance information is attached to the plans.

Answer: b) A complete set of approved plans and specifications is available for every discipline
involved.

Explanation: To ensure compliance with the project’s approved design, it is necessary that all
disciplines (including electrical) have their approved plans and specifications available and
properly filed.



Question 6:
Which of the following best describes “project administration” as it relates to electrical
inspection?
a) Directing the construction crew’s daily activities
b) Ensuring that all administrative documentation (permits, plans, records) is correct and
available
c) Designing the electrical layout for the building
d) Supervising the installation of wiring and conduits

,Answer: b) Ensuring that all administrative documentation (permits, plans, records) is correct
and available

Explanation: Project administration in the context of inspection involves checking that all
required permits, plans, and related documents are properly issued, valid, and available for
review.



Question 7:
An inspector finds that a permit number is missing from the construction documents. What is the
next step?
a) Write a note in the inspection report and proceed with the inspection.
b) Advise the contractor to apply for a new permit immediately.
c) Contact the permitting agency to confirm the permit number and validity.
d) Dismiss the project as non‐compliant.

Answer: c) Contact the permitting agency to confirm the permit number and validity.

Explanation: When documentation is incomplete or appears to be missing critical information,
the inspector should verify the details with the permitting agency rather than assuming
compliance or non‐compliance.



Question 8:
The approved plans for a residential project are dated over a year ago. As an inspector, you
should:
a) Assume that the project is outdated and fail it immediately.
b) Verify if any amendments or addenda have been issued since that date.
c) Request that the plans be re-approved.
d) Ignore the date as long as the work meets the current code.

Answer: b) Verify if any amendments or addenda have been issued since that date.

Explanation: Plans may be updated by addenda or amendments. It is important for the inspector
to confirm that the documents reflect the most current approved information for proper code
evaluation.



Question 9:
Why is record retention important in project administration for electrical inspectors?
a) It ensures that the contractor is billed correctly.
b) It provides a documented history of compliance for review and potential future reference.

, c) It allows inspectors to reuse old inspection reports.
d) It satisfies marketing requirements of the inspection department.

Answer: b) It provides a documented history of compliance for review and potential future
reference.

Explanation: Keeping thorough records—including inspection reports, permits, and plan
approvals—is essential for verifying compliance, supporting corrective actions, and serving as a
historical reference.



Question 10:
Which of the following best describes the role of an electrical inspector with respect to project
administration?
a) Enforcing construction scheduling
b) Verifying documentation, such as permits and approved plans, are in order
c) Supervising the electrical installation crew
d) Designing new electrical systems

Answer: b) Verifying documentation, such as permits and approved plans, are in order

Explanation: An inspector’s role in project administration centers on verifying that all required
documents—including permits and plans—are complete and correct before work proceeds.



Question 11:
If discrepancies are found between the approved plans and the actual construction, the inspector
should:
a) Immediately approve the work if it appears safe.
b) Document the discrepancy and require corrective action.
c) Ignore the discrepancy if it is minor.
d) Close the file without taking any action.

Answer: b) Document the discrepancy and require corrective action.

Explanation: Discrepancies between approved plans and actual work must be formally
documented and corrected to ensure that installations comply with code and the project’s
approved design.



Question 12:
When verifying permit information, an inspector should check:
a) The permit’s expiration date, scope, and any special conditions.

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
nikhiljain22 EXAMS
View profile
Follow You need to be logged in order to follow users or courses
Sold
812
Member since
1 year
Number of followers
30
Documents
19531
Last sold
4 hours ago

3.5

187 reviews

5
60
4
43
3
41
2
11
1
32

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions