A go/no-go decision must be made fairly quickly because:
a) The team needs enough time to create a winning proposal
b) It is largely a gut instinct
c) If a firm prospects correctly, all of their pursuits will be a "go"
d) The BD team needs sufficient time to conduct cold calls - ✔✔a
An MBE firm is required to be __________ owned and controlled by a minority.
a) Greater than 5%
b) At least 51%
c) 100%
d) None of the above - ✔✔b
MBE, WBE, and SDBE Goals are:
Katelyn Whitman, All Rights Reserved © 2025 1
, a) Never required on projects for private organizations
b) Established consistently by the Federal Government for all federal, state, and
municipal projects receiving Federal funds
c) Guidelines that do not need to be followed in project execution
d) Different depending on the state and agency - ✔✔d
This document is a general response for a client to solicit qualified firms for a specific
area of practice or project.
a) Statement of Qualifications
b) Short list
c) Request for Information
d) Proposal - ✔✔a
In a multi-phase selection, it is important to:
a) Change messaging in each phase to keep the client interested
b) Repeat all information given in previous phases in case additional reviewers are
added
c) Define the key message early
d) Focus efforts on the final phase of procurement - ✔✔c