Real time transmission constraints or contingencies may be alleviated with generators operating ______________ - ANSWER off cost out of merit. Monitoring ___________ may give insights into system constraints. - ANSWER Monitoring LMP's PJM calls for _____________ reserves to recover ace so that tie line schedules are maintained. - ANSWER PJM calls on synchronized reserves

Show more Read less
Institution
PJM Generation
Course
PJM Generation









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
PJM Generation
Course
PJM Generation

Document information

Uploaded on
January 22, 2025
Number of pages
11
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

  • pjm sample test
  • pjm

Content preview

PJM Sample Test Review 100% Accurate
Real time transmission constraints or contingencies may be alleviated with generators
operating ______________ - ANSWER off cost out of merit.

Monitoring ___________ may give insights into system constraints. - ANSWER
Monitoring LMP's

PJM calls for _____________ reserves to recover ace so that tie line schedules are
maintained. - ANSWER PJM calls on synchronized reserves

If not cancelled by PJM, the minimum generation alert expires at the end of the
specified ______________. - ANSWER light load period

When PJM declares a hot weather alert, the generation dispatcher should determine if
maintenance can be deferred and notify all generating stations and key personnel. -
ANSWER

During system restoration, the two categories of reserves are dynamic and spinning. -
ANSWER

During system restoration, frequency should be maintained between 59.75 and 61.00
Hertz. - ANSWER

PJM issues a heavy load voltage schedule. Member companies who own generation
facilities should ensure voltage regulators on generating units are in service &
automatic. - ANSWER

A unit being dispatched economically by PJM should set its megawatt output based on
the unit's dispatch rate or desired megawatt level. - ANSWER

A fossil steam unit is considered fuel limited when it is not capable of running at its
maximum capacity for the next 72 hours - ANSWER

During system restoration prior to synchronization of a unit, the dispatcher should
ensure sufficient load is available to stabilize unit operation. - ANSWER

A large unit in an external control area near PJM/PJM West trips. The PJM operator will
see ace remain the same, frequency decrease. - ANSWER

LMPs will change when marginal generator output changes - ANSWER

The two control signals sent by the PJM E M S are regulation and dispatch rate (desired
MW output). - ANSWER

, An all-call is the one-way communication system used to disseminate information to
market operation centers. - ANSWER

Real time bus prices may be monitored using data viewer. - ANSWER

Not offering an available PJM capacity resource into the day ahead market is a violation
of PJMs two settlement market rules. - ANSWER

A unit that fails to start when scheduled, would be classified as an unplanned outage. -
ANSWER

Maximum Generation Emergency is declared by PJM when generation is required
above the highest incremental economic cost. - ANSWER

Maintenance outages are permitted when a unit can be held online until the following
Monday, and system reliability is not affected - ANSWER

If PJM ace shows over-generation, actual imports are less than scheduled. - ANSWER

PJM will request a Supplementary Status Report when a Maximum Generation
Emergency Alert is issued. - ANSWER

If a fossil steam unit has less than 32 hours of fuel at maximum capacity, it should be
bid at maximum emergency. - ANSWER

The loss of a large generation unit on the PJM system can be detected by monitoring
frequency and PJM ace. - ANSWER

A 1000 megawatt unit has tripped in the PJM control area and the PJM ace now
indicates under-generation of 1050 Megawatt. PJM should request 100% synchronized
reserves be loaded. - ANSWER

Alerts are issued in advance of a scheduled load period to allow sufficient time for the
generation dispatcher to prepare for the anticipated capacity shortages - ANSWER

The amount of synchronized reserves must be large enough to cover the loss of the
largest single energy contingency. - ANSWER

When preparing a supplementary status report (SSR), a steam unit that has 30 hours of
fuel remaining. This unit should be reported as a resource limited unit. - ANSWER

PJM responds to capacity shortages by issuing alerts in advance of a scheduled load
period to allow sufficient time for members to prepare for anticipated initial capacity
shortages. - ANSWER

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Lecchris West Virgina University
View profile
Follow You need to be logged in order to follow users or courses
Sold
40
Member since
2 year
Number of followers
15
Documents
3203
Last sold
2 weeks ago
LECCHRIS

3.8

6 reviews

5
2
4
1
3
3
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions