Answers 100% Guaranteed Pass.
In case of ambiguity in the contract language, the intent of the contract will generally be
interpreted against the party who drafted the contract. - Answer✔True
A majority of contractor claims and disputes arise out of poorly drafted or ambiguous contract
documents. - Answer✔True
Generally, the Contractor needs to stop all of its operations and not perform any work on the
project until its claim is resolved. - Answer✔False
Which of the following is a delay caused by the Contractor? - Answer✔Inadequate coordination
of the subcontractors
Which of the following terms is not a type of acceleration as used for the construction projects? -
Answer✔Instant acceleration
According to the supplemental reading, even the best trained and experienced construction
lawyer needs a significant amount of input from his/her client to prepare a construction case. -
Answer✔True
Weather conditions that delay a project are always excusable and compensable. - Answer✔False
Which of the following is not a delay type (for construction projects)? - Answer✔Expected delay
In the contracts where the Contractor waives any rights to impact costs (resulting from the
change orders), the Contractor typically tries to recover the impact costs through the claims
process. - Answer✔True
If there is a conflict between two different provisions of a written agreement, the courts will rule
that the more specific term should govern over the general term. - Answer✔True
.
One of the differences between arbitration and mediation is that a mediator has the final power of
decision whereas an arbitrator does not. - Answer✔False
According to the Supplementary Reading 1 entitled "Things that you Should Know About
Alternate Dispute Resolution", statistics have shown that over 90% of mediations are resolved. -
Answer✔True
1|Page