Answers)
Which theme establishes mechanisms to determine whether the
project is (and remains) desirable, viable, and achievable? - answer
Business Case theme
Which type of risk response only reduces the financial impact of a
risk? - answer Transfer
What PRINCE2 term is used to describe the adoption of PRINCE2
across an organization? - answer Embedding
What PRINCE2 term is used to describe the measurable
improvement resulting from an outcome that is perceived as
positive by one or more stakeholders? - answer Benefit
PRINCE2 consists of four integrated elements: themes, processes,
the project environment, and which other? - answer Principles
Which management product is used to determine how and when a
measurement of the achievement of the project's benefits can be
made? - answer Benefits Review Plan
Which section of the Business Case balances the forecast benefits
against the time, cost, and risk of the project? - answer Investment
appraisal
During which process is version one of the detailed Business Case
created? - answer Initiating a Project
,Which role is responsible for demonstrating that benefits have
occurred? - answer Senior User
What are the five core activities of configuration management? -
answer Planning, identification, control, status accounting, and
verification and audit
Which of the PRINCE2 principles ensures that everyone on the
project team understands what is expected of them? - answer
Defined roles and responsibilities
Which three project interests are represented on the Project Board?
- answer Business, user, and supplier
Which PRINCE2 role is ultimately responsible for the project? -
answer Executive
Which management product documents the justification for
undertaking the project? - answer Business Case
What management product describes a project's approach to
managing uncertainty? - answer Risk Management Strategy
When a team is sited at a different geographic location from the
Project Manager, what role might be used to manage that team? -
answer Team Manager
Which term is used to describe anyone who can affect or be affected
by the project? - answer Stakeholder
During which process is the Communication Management Strategy
created? - answer Initiating a Project
, Which theme defines and implements the means by which the
project will create and verify products that are fit for their purpose?
- answer Quality theme
Which quality review technique role will review and submit
questions about the product under review? - answer Reviewer
Is quality assurance internal or external to the project management
team? - answer External
Which of the PRINCE2 principles ensures efficient and economic use
of management time? - answer Manage by exception
During which process is the Project Brief created? - answer Starting
up a Project
Which management product contains the customer's quality
expectations and acceptance criteria? - answer Project Product
Description
Which is always measurable: the customer's quality expectations or
acceptance criteria? - answer Acceptance criteria
What does PRINCE2 call evidence that has been gathered to show
that quality activities have been carried out? - answer Quality
records
During which process is the Project Product Description first
created? - answer Starting up a Project