31
Cost Variance - correct answer ✔✔the difference between EV and AC to determine of the project is
meeting its budget expectations
Cost Performance Index - correct answer ✔✔a ratio that measures COST efficiency
Schedule Variance - correct answer ✔✔difference between EV and PV to determine if the project is
meeting its schedule expectations or if there is a variance
Schedule Performance Index - correct answer ✔✔a ratio that creates a measure of TIME efficiency
To Complete Performance Index - correct answer ✔✔what the CPI will need for the remainder of the
project if the team intends to finish on budget.
Percent Complete Index - correct answer ✔✔how much the total project work has been completed.
Estimate to Complete - correct answer ✔✔an estimate of how much money will be needed to complete
the project
Estimate at Completion - correct answer ✔✔new forecast of how much more in total the project is
expected to cost once completed
Cost Variance - correct answer ✔✔EV - AC = CV
Cost Performance Index - correct answer ✔✔EV/AC = CPI
Schedule Variance - correct answer ✔✔EV - PV = SV