You are trying to figure out how best to determine estimated activity durations for several tasks. Which
project management method could you use?
a. Critical chain project management (CCPM)
b. Waterfall
c. PERT
d. Command and control - correct answer ✔✔c. PERT
PERT uses a statistical approach to estimate activity duration times.
Because you want to be able to coordinate your project activities, the _________ is the best standard to
use for your restaurant project.
a. PRINCE2
b. PMBOK - correct answer ✔✔b. PMBOK
Closing is a ______ process.
A. NONITERATIVE
B. ITERATIVE - correct answer ✔✔a. noniterative
Closing is noniterative.
Planning is an ________ process.
a. noniterative
, b. iterative - correct answer ✔✔b. iterative
Planning is iterative. The planning process can be stopped after this stage.
Executing is an ______ process.
a. noniterative
b. iterative - correct answer ✔✔b. iterative
Executing is iterative. The execution process can be stopped after this stage.
Initiating is a _____ process.
a. noniterative
b. iterative - correct answer ✔✔a. noniterative
Initiating has to happen regardless of whether the project will be stopped after planning, executing
stages.
Monitoring and controlling are iterative processes. - correct answer ✔✔b. iterative
Monitoring and controlling are iterative. They happen throughout the iterative processes.
Given a project to remodel the waiting room of a doctor's office, the
__________________________________________
tasks would take place during the executing process.
a. writing the WBS and creating the risk register
b. painting and furniture delivery