Which of the following is the strongest reason for terminating a project prior to completion? - correct
answer ✔✔ The project is no longer economically or technically feasible.
By using which of the following can you determine the actual cost of the project? - correct answer ✔✔
Cost reports
During the ---------- stage of team development is where team members are fully comfortable working
together. - correct answer ✔✔ performing
---------- measures the percent complete based on the new Estimate at Completion (EAC). - correct
answer ✔✔ The Percent Complete Index — Cost (PCIC)
---------- is one characteristic of an effective team. - correct answer ✔✔ Unity of purpose
Amit, a project team member at TVX Technologies, is responsible for documenting and archiving all
project-related information to a website so that project stakeholders can access the information as
needed. Amit's task is best described as -----------. - correct answer ✔✔ recording
---------- is the key nonverbal communications methodology used to inform and to document project
information. - correct answer ✔✔ Reporting
------------ is the process of monitoring and changing project execution to ensure that activities are being
executed as planned and will result in meeting the customer requirements. - correct answer ✔✔ Quality
control
By conducting an after action review, an organization can ----------. - correct answer ✔✔ teach current
and future project teams which activities are effective and ineffective
A widely accepted method of measuring project performance and progress of actual cost against the
budgeted/planned cost is called what? - correct answer ✔✔ Earned Value Management