100% correct answers
Which of the following creates a baseline for measuring progress as well as a roadmap for determining
how to get the job done?
a. Budgeting
b. Resource leveling
c. Planning
d. Negotiation - correct answer ✔✔c. planning
Planning creates a baseline for measuring progress well as a roadmap for determining how to get the job
done.
Which of the following is the portion of the scope statement that defines the features and functions of
the project outcome or deliverables?
a. Project sponsor
b. Product scope
c. Project plan
d. Resource histogram - correct answer ✔✔b. product scope
The product scope is the portion of the scope statement that defines the features and functions of the
project outcome or deliverables.
, Which of the following is a characteristic, function, or capability that must be present in the project's
final outcome?
a. Requirements Traceability Matrix
b.Project requirement
c. Critical path
d. Milestone - correct answer ✔✔b. project requirement
A project requirement is a characteristic, function, or capability that must be present in the project's final
outcome.
Which of the following is the two-way process where the people involved share and respond to ideas
and information via verbal, written or nonverbal means?
a. Communication
b. Ethical behavior
c. Teamwork
d. Leadership - correct answer ✔✔a. communication
Communication is an important project management skills and it is the two-way process where the
people involved share and respond to ideas and information via verbal, written or nonverbal means.