_______________activities are activities that can be performed simultaneously because they involve
different resources. - correct answer ✔✔Concurrent
Decreasing ____________________ is possible by Inspecting tasks to see if they can be made shorter. -
correct answer ✔✔Critical Path
To provide a unique representation of each item on the network diagram, you can use which of the
following?
Work Breakdown Structures
Sequencing requirements
Budgets
Label nodes - correct answer ✔✔Label Nodes
Between tasks you can insert _________________ to help shorten the overall duration. - correct answer
✔✔Lead Time
The ___________________ used to complete project tasks can come from within or outside of the
organization hosting the project. - correct answer ✔✔Resources
___________________________ depend on project deliverables, project constraints, milestones,
budgets, etc. - correct answer ✔✔Task Relationships
The rows down the left margin in a ____________________ display key activities or stages of the project
in sequence. - correct answer ✔✔GNATT Chart
What is the concept that suggests the more often a person completes a task, the better he or she
becomes at completing that task called?
, Learning curve
Beta distribution
Work Breakdown Structure (WBS)
One-point estimate - correct answer ✔✔Learning Curve
Which of the following is the logical relationship where the successor task cannot be completed until the
first task is completed?
Start-to-start relationships
Finish-to-finish relationship
Finish-to-start relationships
Start-to-finish relationships - correct answer ✔✔Finish-to-finish relationship
You can reduce critical path by eliminating _____________ that may not be required to achieve the
desired end result. - correct answer ✔✔Task
The goal of ___________________________ is to get the project delivered faster. - correct answer
✔✔Schedule compression
As the project team develops the activity ____________________, they may divide activities or identify
additional activities that need to be added to the WBS. - correct answer ✔✔duration estimates
A _______________________ is when you start assigning dates based on the earliest start date, adding
dates based on estimates for each task in the diagram. - correct answer ✔✔forward pass
Which of the following is critical for creating accurate and realistic project plans and schedules?
Task relationships
Finish-to-start relationships
Successor activities