CertifiedAssociateProjectManager (CAPM)PrepExam Questions&Answers. Which of the following depicts the three key skil sets in the PMI Talent Triangle? - Correct Answer Leadership, Strategic and Business Management and technical project Management Select the best description of the initiating Process Group. - Correct Answer The process(es) performed to define a new project or a new phase of an existing project by obtaining authorization to start the project or phase. Which of the following are examples of the internal and external enterprise environmental factors? - Correct Answer Information technology software and marketplace conditions. Using the data below, assuming the all future work will be performed at the budgeted rate, the estimate at completion (EAC) is: BAC = 200 PV = 100 AC = 120 EV = 80 - Correct Answer 24

Show more Read less
Institution
Certified Associate
Course
Certified Associate









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Certified Associate
Course
Certified Associate

Document information

Uploaded on
December 16, 2024
Number of pages
14
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Content preview

Certified Associate Project Manager (CAPM) Prep Exam
Questions & Answers.

Which of the following depicts the three key skil sets in the PMI Talent Triangle? - Correct
Answer Leadership, Strategic and Business Management and technical project
Management


Select the best description of the initiating Process Group. - Correct Answer The
process(es) performed to define a new project or a new phase of an existing project by
obtaining authorization to start the project or phase.


Which of the following are examples of the internal and external enterprise environmental
factors? - Correct Answer Information technology software and marketplace conditions.


Using the data below, assuming the all future work will be performed at the budgeted rate,
the estimate at completion (EAC) is:


BAC = 200
PV = 100
AC = 120
EV = 80 - Correct Answer 240


You are involved in the process of communicating and working with stakeholders to meet
their needs/expectations, address issues as the occur, and foster appropriate
Stakeholder engagement in project activities throughout the project life cycle. This is
known as: - Correct Answer Manage Stake holder Engagement


Outputs from the Estimate Activity Resource process include which of the following? -
Correct Answer Identification from the type and quantities of resources required for each
activity in a work package


What output is part of the Control Scope process? - Correct Answer Change Requests


Which of the following describes a schedule compression technique used to shorten the
schedule duration for the least incremental cost by adding resources? - Correct Answer
Crashing

, Which of the Following is the process of establishing the policies, procedures, and
documentation for planning, developing, managing, executing, and controlling the project
schedule? - Correct Answer Plan Schedule Management


An output of the Define Scope Process is: - Correct Answer Project Scope Statement


Which of the following is an output to the Sequence Activities process? - Correct Answer
Project Schedule network diagram


What Process involves leading and performing the work defined n the project
management plan and implementing approved changes to achieve the project's
objectives? - Correct Answer Direct and Manage Project Work


SWOT analysis has all of the following characteristic EXCEPT: - Correct Answer It
identifies strengths and weaknesses of the organization, regardless of the specific project
or the general business area.


The Implement Risk Responses process ensures that agreed-upon risk response are
executed as planned in order to do what? - Correct Answer Address overall project risk
exposure,minimize individual project threats, and maximize individual project
opportunities.


Which of the following resources ensure that the project receives the best resources
possible in the required time frame and until their responsibilities are complete? - Correct
Answer Functional manager


Training has all of the following characteristics EXCEPT: - Correct Answer Cost
associated with training should never be included in the project budget as add skills will be
used beyond one project.


Project Communication Management includes all of the following EXCEPT: - Correct
Answer Resource Management is concentrated on allocating and utilizing the physical
resources needed for successful completion of the project in an efficient and effective
way.


Which of the following are interpersonal and team skills used as part of the Manage
Stakeholder Engagement process? - Correct Answer Negotiation and conflict
management

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Lectjosh Chamberlain College Nursing
View profile
Follow You need to be logged in order to follow users or courses
Sold
82
Member since
2 year
Number of followers
68
Documents
5713
Last sold
2 months ago
expertee

Hello my name is joe, I am very friendly and experienced tutor dedicated to my teaching work. If you need any kind of help then you can contact me with any questions about your course .I can help you with everything - tests, quizzes, exams, db threads and so on. Just ask me if you want to get an A on your courses. Anyway Welcome to Tutoring with Experience and Enthusiasm! I am thrilled to have the opportunity to help you with best study guides and assignments. Be prepared.

Read more Read less
3.8

12 reviews

5
6
4
1
3
3
2
1
1
1

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions