Answers.
what is an anti-pattern for the IP iteration?
- to plan work for the IP iteration during PI planning
- to allow for sufficient capacity in the program roadmap
- to ensure all stories and teams' PI plans are completed prior to the IP iteration
- to minimize lost capacity when people are on vacation or holidays
-to wait for the IP iteration to fix defects - ANS - to plan work for the IP iteration during PI
planning
-to wait for the IP iteration to fix defects
What is the purpose of the plan-do-check-adjust cycle?
- To provide regular, predictable dev cadence to produce an increment of value
- To give the ART members a process tool to keep the train on the tracks
- To create a continuous flow of work to support the delivery pipeline
- To allow the team to perform some final backlog refinement for upcoming iteration
planning - ANS - To provide regular, predictable dev cadence to produce an increment of
value
Which meeting should the Scrum Master attend (not facilitate)?
- Iteration Review
- Scrum of Scrums
- Daily Stand-Up
- PO sync - ANS - Scrum of Scrums
Scrum masters help remove impediments, foster an environment for high-performing
team dynamics and what else?
, - Relentlessly improve
- Continuously deliver
- Form and re-form teams
- Estimate stories - ANS - Relentlessly improve
Each PI planning meeting evolves over time, and ending PI planning with a Retrospective
will help to do what?
- Fine tune the Economic Framework
- Meet compliance more rapidly
- Lengthen the Architectural Runway
- Continuously improve - ANS - Continuously improve
What is one truth about teams?
- Development teams can manage daily interruptions
- Products are more robust when individuals on teams have specific skill sets
- Changes in team composition do not impact productivity
- Teams are more productive than the same number of individuals - ANS - Teams are
more productive than the same number of individuals
Which type of enabler does a System Architect review during a System Demo?
- Enabler Capabilities
- Enabler Features
- '' Stories
- '' Portfolio Epics - ANS - Enabler stories
Who can change the backlog during an iteration?
- Agile Team
- Scrum master