The thermometer on a hot water supply boiler shall? - ACCURATE
ANSWERS✔✔ Indicate water temperature at or near boiler outlet
(NBIC PRT 2 PAR. 2.2.10.6.l.3)
1. What type of Nondestructive examination is used for volumetric
examination of welds and base materials (metallic and nonmetallic) for
detection of flaws and measure material thickness? - ACCURATE
ANSWERS✔✔ Ultrasonic (NBIC PRT 2 PAR. 4.2.4)
What requirements shall be followed when performing a liquid pressure
test following repair or alteration of a pressure retaining item to assess
pressure boundary integrity? - ACCURATE ANSWERS✔✔ (NBIC PRT
2 PAR. 4.3.1)
, The owner of an installed pressure retaining item where creep is a
consideration should____. - ACCURATE ANSWERS✔✔ ...seek
competent technical advice to determine which of the condition
assessment methods can be used to ensure safe operation and
determination of the next inspection interval for the pressure-retaining
item when elevated service temperature is a consideration. (NBIC PRT 2
PAR. 44.4.8.1.b)
When evaluating a pressure-retaining item with local thin areas, what
should be considered? - ACCURATE ANSWERS✔✔ View list via
(NBIC PRT 2 PAR. 4.4.8.7)
Personnel performing nondestructive examination and test methods shall
have? - ACCURATE ANSWERS✔✔ Training and certification (NBIC
PRT 2 PAR. 4.2.c)
Eddy current nondestructive testing measures? - ACCURATE
ANSWERS✔✔ Changes in magnetic field (NBIC PRT 2 PAR. 4.2.6)
Who is responsible for the selection and application of a suitable Fitness
for Service or Condition Assessment Methodology? - ACCURATE
ANSWERS✔✔ Owner or user (NBIC PRT 2 PAR. 4.4.3.a)
The maximum period between internal inspections or a complete
Inservice evaluations of pressure-retaining item shall not exceed? -
ACCURATE ANSWERS✔✔ ½ estimated remaining service life (NBIC
PRT 2 PAR. 4.4.7.a)