100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

Class A/B Operator for Underground Storage Tank. Study Exam Questions With Correct Answers

Rating
-
Sold
-
Pages
7
Grade
A+
Uploaded on
02-12-2024
Written in
2024/2025

©BRAINBARTER EXAM SOLUTIONS 2024/2025 ALL RIGHTS RESERVED. 1 | P a g e Class A/B Operator for Underground Storage Tank. Study Exam Questions With Correct Answers The Class A and Class B certification must be renewed every: - answer5 years UST financial responsibility requirements apply to what? - answer600 gallon used oil tank Secondary Containment is required for what? - answerNew UST Systems, Piping in contact with the ground, and Replacement UST A Class A operator shall maintain the records of UST site inspections for a *minimum* of: - answer3 years New owners of an existing UST system shall register the UST system with DEQ/LARA within what period from date of ownership? - answer30 days UST systems with cathodic protection should be inspected for proper operation by a qualified cathodic protection tester on the following schedule: - answerEvery three years UST systems with impressed current cathodic protection systems must be inspected at a minimum: - answerEvery 60 days Within what period after a repair should a cathodically protected UST system be tested to ensure it is working properly? - answer6 months Pressurized underground piping that routinely contains regulated substances shall be monitored for releases in a manner that meets what requirements? - answerBe equipped with a line leak detector, and have an annual line tightness test A suspected release must be confirmed to the DEQ/LARA within: - answer7 days What actions are required in MUSTR when there is a spill or overfil of petroleum or hazardouz substances that result in a release into groundwater, surface water, or substance soils? - ©BRAINBARTER EXAM SOLUTIONS 2024/2025 ALL RIGHTS RESERVED. 2 | P a g e answerNotify DEQ/LARA of a confirmed release, Immediately clean up the spill or overfill, and Contain the spill To permanently close a tank, an owner and operator shall: - answerRemove the tank from the ground, Fill with an inert solid if removal jeopardizes the building structure integrity, and Empty and clean the tank by removing all liquids and accumulated sludge and purge it of all vapors If you have 100 or fewer tanks, financial responsibility is required in the aggregate the amount of: - answer$1 Million Petroleum marketers are required to have finanical responsibility to cover X dollars per occurence. X is.... - answer$1 Million Can an owner use pollution liability insurance as a means of financial responsibility? - answerYes An automatic tank gauge must be able to detect a leak of X gallons per hour. X is: - answer0.2 gallons per hour Statistical Inventory reconciliation (SIR) analyzes the following as a means of leak detection: - answerInventory, Delivery and Dispensing Manual tank gauging can be used as the 'sole' means of a leak detection for tanks that are X gallons or less in capacity. X is: - answer550 gallons Check if the following statement is true or false: "A third party evaluation of a statistical inventory reconciliation is good for any type of tank and product." - answerFalse Automatic line leak detectors must be able to detect a leak of at least X gallons per hour at a line pressure of 10 psi witin one hour. X is: - answer3 gallons per hour Line testing of piping shall be capable of detecting X gallons per hour leak rate at 1 and a half times the operating pressure. X is: - answer0.1 gallons per hour What actions are not appropriate when when the owner/operator becomes aware of a spill or overfill? - answerDrain the spill to the storm sewer or nearby ditch Upon confirmation of a release to the soil/groundwater/surface water the operator shall: - answerReport the release to the DEQ within 24 hours, by fax or phone A Class B operator shall not be responsible for more than the following facilities: - answer45 facilities What is the minimum frequency of site inspections to assure operational compliance? - answerQuarterly

Show more Read less
Institution
Class A/B Operator
Course
Class A/B Operator









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Class A/B Operator
Course
Class A/B Operator

Document information

Uploaded on
December 2, 2024
Number of pages
7
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

©BRAINBARTER EXAM SOLUTIONS 2024/2025

ALL RIGHTS RESERVED.



Class A/B Operator for Underground
Storage Tank. Study Exam Questions With
Correct Answers


The Class A and Class B certification must be renewed every: - answer✔5 years

UST financial responsibility requirements apply to what? - answer✔600 gallon used oil tank

Secondary Containment is required for what? - answer✔New UST Systems, Piping in contact
with the ground, and Replacement UST
A Class A operator shall maintain the records of UST site inspections for a *minimum* of: -
answer✔3 years
New owners of an existing UST system shall register the UST system with DEQ/LARA within
what period from date of ownership? - answer✔30 days
UST systems with cathodic protection should be inspected for proper operation by a qualified
cathodic protection tester on the following schedule: - answer✔Every three years
UST systems with impressed current cathodic protection systems must be inspected at a
minimum: - answer✔Every 60 days
Within what period after a repair should a cathodically protected UST system be tested to
ensure it is working properly? - answer✔6 months
Pressurized underground piping that routinely contains regulated substances shall be
monitored for releases in a manner that meets what requirements? - answer✔Be equipped
with a line leak detector, and have an annual line tightness test

A suspected release must be confirmed to the DEQ/LARA within: - answer✔7 days
What actions are required in MUSTR when there is a spill or overfil of petroleum or hazardouz
substances that result in a release into groundwater, surface water, or substance soils? -



1|Page

, ©BRAINBARTER EXAM SOLUTIONS 2024/2025

ALL RIGHTS RESERVED.
answer✔Notify DEQ/LARA of a confirmed release, Immediately clean up the spill or overfill, and
Contain the spill

To permanently close a tank, an owner and operator shall: - answer✔Remove the tank from the
ground, Fill with an inert solid if removal jeopardizes the building structure integrity, and Empty
and clean the tank by removing all liquids and accumulated sludge and purge it of all vapors
If you have 100 or fewer tanks, financial responsibility is required in the aggregate the amount
of: - answer✔$1 Million
Petroleum marketers are required to have finanical responsibility to cover X dollars per
occurence. X is.... - answer✔$1 Million
Can an owner use pollution liability insurance as a means of financial responsibility? -
answer✔Yes

An automatic tank gauge must be able to detect a leak of X gallons per hour. X is: - answer✔0.2
gallons per hour
Statistical Inventory reconciliation (SIR) analyzes the following as a means of leak detection: -
answer✔Inventory, Delivery and Dispensing
Manual tank gauging can be used as the 'sole' means of a leak detection for tanks that are X
gallons or less in capacity. X is: - answer✔550 gallons
Check if the following statement is true or false: "A third party evaluation of a statistical
inventory reconciliation is good for any type of tank and product." - answer✔False
Automatic line leak detectors must be able to detect a leak of at least X gallons per hour at a
line pressure of 10 psi witin one hour. X is: - answer✔3 gallons per hour
Line testing of piping shall be capable of detecting X gallons per hour leak rate at 1 and a half
times the operating pressure. X is: - answer✔0.1 gallons per hour
What actions are not appropriate when when the owner/operator becomes aware of a spill or
overfill? - answer✔Drain the spill to the storm sewer or nearby ditch
Upon confirmation of a release to the soil/groundwater/surface water the operator shall: -
answer✔Report the release to the DEQ within 24 hours, by fax or phone

A Class B operator shall not be responsible for more than the following facilities: - answer✔45
facilities
What is the minimum frequency of site inspections to assure operational compliance? -
answer✔Quarterly

2|Page

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Brainbarter Kaplan University
View profile
Follow You need to be logged in order to follow users or courses
Sold
325
Member since
2 year
Number of followers
153
Documents
22254
Last sold
1 week ago
A+ STUDY MATERIALS.

We offer a wide range of high-quality study materials, including study guides practice exams and flashcards. WELCOME.

3.5

54 reviews

5
21
4
8
3
12
2
4
1
9

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions