100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

CAPM Questions, Answers 100% Verified 2024/2025

Rating
-
Sold
-
Pages
5
Grade
A+
Uploaded on
20-11-2024
Written in
2024/2025

CAPM Questions, Answers 100% Verified 2024/2025

Institution
CFA - Chartered Financial Analyst
Course
CFA - Chartered Financial Analyst









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
CFA - Chartered Financial Analyst
Course
CFA - Chartered Financial Analyst

Document information

Uploaded on
November 20, 2024
Number of pages
5
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

CAPM Questions, Answers 100% Verified 2024/2025
Initiating
Planning
5 process groups Executing
Monitoring and Controlling
Closing

Integration
Scope
Time
Cost
Quality
ten knowledge areas
HR
Communications
Risk
Procurement
Stakeholder management

total float formula total float = late finish - early finish

bell curve - symmetrical distribution - 50%
chance of falling below the mean and 50%
normal distribution chance of falling above the mean
(1sigma=68.27%. 2sigma = 95.45%. 3sigma=
99.73%)

when there are 3 possible values w/ equal probability - distribution is a triangle.
triangular distribution
A= lowest value, B= highest value, M = most likely value

triangular distribution w/ more weight given to the most likely estimate (can be
beta distribution (PERT) asymmetrical). O = optimistic estimate, ML=most likely estimate, P=pessimistic
estimate

mean for a beta distribution mean = (O + 4ML + P)/6

standard deviation for beta distribution standard deviation = (P-O)/6

project mean is the sum of the means of the individual tasks. project standard
statistical sums
deviation is the square root of the project variance

used to monitor the progress of a project and is an analytical technique. uses 3
earned value management
independent values - PV, AC, EV

the budget or the portion of the approved cost estimate planned to be spent
planned value (PV)
during a given period

the total of direct and indirect costs incurred in accomplishing work during a
actual cost (AC)
given period

earned value (EV) the budget for the work accomplished in a given period

cost variance (CV) CV = EV - AC

schedule variance (SV) SV = EV - PV

cost performance index (CPI) CPI = EV/AC

schedule performance index (SPI) SPI = EV/PV

positive CV indicates, negative CV costs are below budget, costs are overrun
indicates

positive SV indicates, negative SV a project is ahead of schedule, a project is behind schedule
indicates

CPI greater than 1.0 indicates costs are below budget

SPI greater than 1.0 indicates project is ahead of schedule




1/5

, CPI less than 1.0 indicates costs are over budget

SPI less than 1.0 indicates a project is behind schedule

the amount we expect the total project to cost on completion and as of the "data
estimate at completion (EAC)
date" (time now)

new estimate technique for finding EAC EAC = AC/new estimate for remaining work

the actual performance to date shows that the original estimates were
new estimate is most applicable when: fundamentally flawed or when they are no longer accurate because of changes in
conditions relating to the project

original estimate technique for finding EAC = AC/(BAC - EV)
EAC

actual variances to date are seen as being the exception, and the expectations for
original estimate is most applicable when: the future are that the original estimates are more reliable than the actual work
effort efficiency date

performance estimate low technique for EAC = AC + (BAC - EV)/CPI or EAC = BAC/CPI
finding EAC

performance estimate low formula is future variances are projected to approximate the same level as current variances
most applicable when:

performance estimate high technique for EAC = AC + (BAC - EV) / (CPI)(SPI)
finding EAC

performance estimate high formula is the project is over budget and the schedule impacts the work remaining to be
most applicable when: completed

BAC budget at completion. the total budgeted cost of all approved activities

estimate to complete - the estimate for completing the remaining work for a
ETC
scheduled activity

ETC when past variances are considered ETC = BAC - EV
to be atypical

ETC when prior variances are considered ETC = (BAC - EV)/CPI
to be typical of future variances

communications channels channels = (n(n-1))/2. n - number of ppl

if 7 or more observations occur in one direction, or a run of 7 observations occurs
rule of seven either above or below the mean, they should be investigated to determine if they
have an assignable cause.

the entire value of a business - the total sum of all tangible and intangible
business value
elements

project team members are physically located close to one another in order to
colocation
improve communications, working relations, and productivity

constraint a restriction or limitation that may force a certain course of action or inaction

external or internal factors that can influence a project's success. includes
controllable factors such as the tools used in managing project within the org, or
enterprise environmental factors
uncontrollable factors that have to be considered by the project manager such as
market conditions or corporate culture

a specific activity or application of a skill, tool, or technique that has been proven
good practice
to contribute positively to the execution of a process

ongoing work performed by ppl, constrained by resources, planned, executed,
operations
monitored, and controlled. unlike a project bc they are repetitive

any formal or informal processes, plans, policies, procedures, guidelines, and
organizational process assets ongoing or historical project info such as lessons learned, measurement data,
project files, and estimates vs actuals



2/5
$9.49
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
Learningnook

Get to know the seller

Seller avatar
Learningnook Stanford University
View profile
Follow You need to be logged in order to follow users or courses
Sold
0
Member since
1 year
Number of followers
0
Documents
49
Last sold
-
Study Zone: Summaries & Practice Papers

Find carefully crafted topic summaries and practice papers to support you in mastering concepts. Mathemtics|| Finance|| Psychology|| Nursing||Human resource Management I am passionate about helping you learn effectively and achieve your academic goals with confidence.

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions