100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.6 TrustPilot
logo-home
Exam (elaborations)

PMBOK Chapter 7 Project Cost Management Questions And Answers

Rating
-
Sold
-
Pages
5
Grade
A+
Uploaded on
20-11-2024
Written in
2024/2025

PMBOK Chapter 7 Project Cost Management Questions And Answers...

Institution
PMBOK Chapter 7 Project Cost Management
Course
PMBOK Chapter 7 Project Cost Management









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
PMBOK Chapter 7 Project Cost Management
Course
PMBOK Chapter 7 Project Cost Management

Document information

Uploaded on
November 20, 2024
Number of pages
5
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

  • pmbok

Content preview

PMBOK Chapter 7 Project Cost Management
Questions And Answers


Project Cost Management includes all of the following processes EXCEPT

Level resources



The cost management plan has all of the following characteristics EXCEPT:

It is based on project cost estimates and is separate from the project management plan



All of the following are true about cost estimates EXCEPT:

Information in the risk register should not be considered in cost estimates, because
risks can be either considered threats or opportunities and their impacts tend to
balance out



An activity cost estimate includes all of the following resource categories EXCEPT:

Time shortages



Parametric estimating involves:

Using a statistical relationship between relevant historical data and other variables to
calculate a cost estimate for project work



Analogous cost estimating:

The actual cost of previous, but similar projects serves as basis for determining the cost
estimate of the current project.



Which of the following represents processes concerned with establishing and
controlling the cost baseline?

, Determine Budget and control costs



The cost baseline has all of the following characteristics EXCEPT:

It shows the actual cost expenditures throughout the project life cycle



The following are included in project cost control EXCEPT:

Allocation of overall estimates to lower work packages to establish the cost baseline



Image 1: You have been promoted to the position of project manager on a large project,
due to the abrupt transfer of the previous PM. On the first day in your new, exciting
position, you find a folder on your desk entitled: Earned Value Management. In that
folder, you find only the chart related to your project with the data date of a few days
ago:

The project is over budget and probably behind schedule.



BAC = 200

PV = 100

AC = 120

EV = 80



Assuming all future work will be performed at the budgeted rate, the estimate at
completion (EAC) is:

240



BAC = 200

PV = 100

AC = 120

EV = 80

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Easton West Virgina University
View profile
Follow You need to be logged in order to follow users or courses
Sold
507
Member since
2 year
Number of followers
221
Documents
22905
Last sold
5 days ago

3.9

111 reviews

5
53
4
21
3
21
2
7
1
9

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions