PJM Generator Exam Study Guide Questions and Answers 100% Pass The purpose of the Deploy All Resources Action is to instruct all generating resources to be on line and at full output _________ - ANSWER-immediately upon receipt of dispatch instruction A Heavy Load Voltage Schedule Warning has been issued for the PJM RTO. Generation Operators should: - ANSWER-Ensure all unit voltage regulators are in service PJM can issue the Deploy All Resources Action for________ - ANSWER-the entire RTO, specific Control Zones or a subset of a Control Zone if transmission limitations exist Under the National Terrorism Advisory System (NTAS) there are 2 types of alerts: Elevated Threat Alert and __________. - ANSWER-Imminent Threat Alert A Geomagnetic Disturbance Warning is issued by PJM when the NOAA has issued a warning or an alert for a potential geo-magnetic storm of severity _______ or greater. - ANSWER-K7 Copyright ©SOPHIABENNETT 2025 ACADEMIC YEARALL RIGHTS RESERVED. Page 2/8 The Generating Capacity reported on a Supplementary Status Report (SSR) includes which of the following? (Select 2) - ANSWER-Capacity from offline Hydro and CT units that can be synchronized within 10 minutes. Total Capacity from online Generation. What is the requested response time for members to reply to a request for SSR data? - ANSWER-10 Minutes If a PJM Member has received reports of a terrorism or sabotage threat to their facilities, they would notify whom at PJM (in addition to NERC and the DOE) to share this information? - ANSWER-The PJM Shift Supervisor What is the purpose of a capacity emergency warning? (Select 2) - ANSWER-To keep Members informed of actual capacity shortages or contingencies that may jeopardize reliability during real time operations. To ask Members to take specific actions in order to provide relief to the PJM system PJM has issued a Minimum Generation Alert. Your current generation output is 200 MW. The Economic Minimum is 150 MW and Emergency Minimum is 125 MW. How much ERG should be reported for this unit? - ANSWER-25 MW A Manual Load Dump Warning will be issued when: - ANSWER-Primary Reserve is less than the largest generating unit or the loss of a transmission facility jeopardizes reliability after all possible measures have been taken to increas

Show more Read less
Institution
PJM Generation Dispatcher
Course
PJM Generation Dispatcher









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
PJM Generation Dispatcher
Course
PJM Generation Dispatcher

Document information

Uploaded on
November 19, 2024
Number of pages
8
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

PJM Generator Exam Study Guide
Questions and Answers 100% Pass

The purpose of the Deploy All Resources Action is to instruct all generating resources

to be on line and at full output _________ - ANSWER✔✔-immediately upon receipt of

dispatch instruction


A Heavy Load Voltage Schedule Warning has been issued for the PJM RTO. Generation

Operators should: - ANSWER✔✔-Ensure all unit voltage regulators are in service


PJM can issue the Deploy All Resources Action for________ - ANSWER✔✔-the entire

RTO, specific Control Zones or a subset of a Control Zone if transmission limitations

exist


Under the National Terrorism Advisory System (NTAS) there are 2 types of alerts:

Elevated Threat Alert and __________. - ANSWER✔✔-Imminent Threat Alert


A Geomagnetic Disturbance Warning is issued by PJM when the NOAA has issued a

warning or an alert for a potential geo-magnetic storm of severity _______ or greater. -

ANSWER✔✔-K7




Copyright ©SOPHIABENNETT 2025 ACADEMIC YEARALL RIGHTS RESERVED. Page 1/8

, The Generating Capacity reported on a Supplementary Status Report (SSR) includes

which of the following? (Select 2) - ANSWER✔✔-Capacity from offline Hydro and CT

units that can be synchronized within 10 minutes.


Total Capacity from online Generation.


What is the requested response time for members to reply to a request for SSR data? -

ANSWER✔✔-10 Minutes


If a PJM Member has received reports of a terrorism or sabotage threat to their facilities,

they would notify whom at PJM (in addition to NERC and the DOE) to share this

information? - ANSWER✔✔-The PJM Shift Supervisor


What is the purpose of a capacity emergency warning? (Select 2) - ANSWER✔✔-To

keep Members informed of actual capacity shortages or contingencies that may

jeopardize reliability during real time operations. To ask Members to take specific

actions in order to provide relief to the PJM system


PJM has issued a Minimum Generation Alert. Your current generation output is 200

MW. The Economic Minimum is 150 MW and Emergency Minimum is 125 MW. How

much ERG should be reported for this unit? - ANSWER✔✔-25 MW


A Manual Load Dump Warning will be issued when: - ANSWER✔✔-Primary Reserve

is less than the largest generating unit or the loss of a transmission facility jeopardizes

reliability after all possible measures have been taken to increase reserves



Copyright ©SOPHIABENNETT 2025 ACADEMIC YEARALL RIGHTS RESERVED. Page 2/8

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
SophiaBennett Howard Community College
View profile
Follow You need to be logged in order to follow users or courses
Sold
131
Member since
1 year
Number of followers
5
Documents
9104
Last sold
4 days ago
EXAM GAME-CHANGER

Exam Questions and Answers Section : Study Like a Pro, Study Smart, Study with Sophia.

3.7

26 reviews

5
10
4
5
3
7
2
1
1
3

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions