PJM Generation Dispatcher Sample Exam Questions and Answers 100% Pass Real time transmission constraints or contingencies may be alleviated with generators operating : A. below 60 hertz B. on a new price curve C. on a new cost curve D. off cost ( out of merit) - ANSWER-D. off cost ( out of merit ) Monitoring LMP may give insights into : A. system constraints B. system voltage C. system frefuency D. time error - ANSWER-A. system constraints Copyright ©SOPHIABENNETT 2025 ACADEMIC YEARALL RIGHTS RESERVED. Page 2/15 PJM calls for which of the following to recover the ACE so that tie line schedules are maintained ? A. IRC ( instantaneous reserve check ) B. synchronized Reserves C. supplemential reserves D. minimun generation calculation - ANSWER-B. synchronized Reserves If not cancelled by PJM , the minimum generation alert expires : A. at the end of the specified light load period B. when notified by NERC C. 12 hours after the alert was issued D. after a 24 hour period - ANSWER-A. at the end of the specified light load period When PJM declares a hot weather alert , the generation dispatcher should 1. determine if maintenance can be deferred 2. notift transmission operators Copyright ©SOPHIABENNETT 2025 ACADEMIC YEARALL RIGHTS RESERVED. Page 3/15 3. notify all generating stations and key personnel 4. direct all generating stations to reduce output A. 1 and 2 only B. 1 and 3 only C. 2 and 4 only D. 3 and 4 only - ANSWER-B. 1 and 3 only 1. determine if maintenance can be deferred 3. notify all generating stations and key personnel During system restoration, the two categories of reserves are : A. dynamic and secondary B. spinning and quick start C. dynamic and spinning D. spinning and primary - ANSWER-C. dynamic and spinning During system restoration, frequency should be maintained between : Copyright ©SOPHIABENNETT 2025 ACADEMIC YEARALL RIGHTS RESERVED. Page 4/15 A. 59.50 and 60.00 hertz B. 59.75 and 61.50 hertz C. 59.75 and 61.00 hertz D. 59.50 and 60.50 hertz - ANSWER-C. 59.75 and 61.00 hertz PJM issues a heave load voltage schedule. Member companies who own generation facilities should : A. remove 230 kV capacitors from service B. ensure voltage regulators on generating units are in service on automatic C. inform transmission providers to have marketers in their areas cut transactions D. instruct generating stations to curtail nonessential building loads - ANSWER-B. ensure voltage regulators on generating units are in service on automatic A unit being dispatched economically by PJM should set its MW output based on the : A. LMP at generator bus B. LMP in the units zone C. units dispatch rate or desired MW level Copyright ©SOPHIABENNETT 2025 ACADEMIC YEARALL RIGHTS RESERVED. Page 5/15 D. generation owners discretion - ANSWER-C. units dispatch rate or desired MW level A fossil steam unit is considered fuel limited when it is not capable of running at its maximum capacity for the next : A. 16 hours B. 36 hours C. 72 hours D. 120 hours - ANSWER-C. 72 hours During system restoration prior to synchronization of a unit, the dispatcher should ensure sufficient load is available to : A. economize unit operation B. maximize unit operation C. stabilize unit operation D. minimize unit operation - ANSWER-C. stabilize unit operat

Show more Read less
Institution
PJM Generation Dispatcher
Course
PJM Generation Dispatcher









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
PJM Generation Dispatcher
Course
PJM Generation Dispatcher

Document information

Uploaded on
November 19, 2024
Number of pages
15
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

PJM Generation Dispatcher Sample Exam
Questions and Answers 100% Pass

Real time transmission constraints or contingencies may be alleviated with generators

operating :




A. below 60 hertz


B. on a new price curve


C. on a new cost curve


D. off cost ( out of merit) - ANSWER✔✔-D. off cost ( out of merit )


Monitoring LMP may give insights into :




A. system constraints


B. system voltage


C. system frefuency


D. time error - ANSWER✔✔-A. system constraints




Copyright ©SOPHIABENNETT 2025 ACADEMIC YEARALL RIGHTS RESERVED. Page 1/15

, PJM calls for which of the following to recover the ACE so that tie line schedules are

maintained ?




A. IRC ( instantaneous reserve check )


B. synchronized Reserves


C. supplemential reserves


D. minimun generation calculation - ANSWER✔✔-B. synchronized Reserves


If not cancelled by PJM , the minimum generation alert expires :




A. at the end of the specified light load period


B. when notified by NERC


C. 12 hours after the alert was issued


D. after a 24 hour period - ANSWER✔✔-A. at the end of the specified light load period


When PJM declares a hot weather alert , the generation dispatcher should




1. determine if maintenance can be deferred


2. notift transmission operators



Copyright ©SOPHIABENNETT 2025 ACADEMIC YEARALL RIGHTS RESERVED. Page 2/15

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
SophiaBennett Howard Community College
View profile
Follow You need to be logged in order to follow users or courses
Sold
131
Member since
1 year
Number of followers
5
Documents
9104
Last sold
4 days ago
EXAM GAME-CHANGER

Exam Questions and Answers Section : Study Like a Pro, Study Smart, Study with Sophia.

3.7

26 reviews

5
10
4
5
3
7
2
1
1
3

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions